The Supreme Court addressed whether a writ appellate court can restrict an Arbitral Tribunal’s jurisdiction by directing it to adjudicate claims strictly according to contract terms when examining a terminated works contract. Partially clarifying the Telangana High Court Division Bench’s order, the apex bench ruled that a court exercising judicial review under Article 226 cannot pre-determine or constrain the scope of the Arbitrator’s inquiry under Section 16 of the Arbitration and Conciliation Act, 1996. The Court emphasized that under the principle of kompetenz-kompetenz, the Arbitral Tribunal possesses the exclusive competence to rule on its own jurisdiction—including whether the dispute over contract termination constitutes an “excepted matter” under Clause 63 of the General Conditions of Contract (GCC)—without being fettered by pre-emptive judicial observations.
- Contractual Background: South Central Railway awarded a track-doubling contract to the appellant, which was later terminated under Clause 62 of the GCC, prompting a legal challenge by the appellant.
- High Court Proceedings: While the Single Judge dismissed the appellant’s writ petition on the ground of an alternative arbitration remedy while remarking on the validity of termination, the Division Bench removed that finding but conditioned the arbitration with strict adherence to contract terms.
- Core Legal Question: The appeal tested whether the High Court’s directive traveled beyond judicial review under Article 226 and infringed upon the Arbitral Tribunal’s statutory powers under Section 16 of the Arbitration Act.
- Excepted Matters and GCC Clauses: A joint reading of Clause 63 and Clause 64 of the GCC indicates that while “excepted matters” are excluded from arbitration, the validity of decisions regarding them remains open to judicial review, though an appointing or writ court cannot micro-manage the tribunal’s mandate.
- Statutory Principle of Kompetenz-Kompetenz: Under Section 16 of the Arbitration and Conciliation Act, 1996, the tribunal is empowered to rule on its own jurisdiction and the validity of the arbitration agreement, a principle insulated from unwarranted pre-reference judicial interference.
- Final Clarification: The Supreme Court disposed of the appeal by clarifying that the High Court’s directions shall not restrict the Arbitral Tribunal’s authority to independently adjudicate the dispute surrounding the contract’s termination.
2026 INSC 976
M/s. GVV Constructions Private Limited v. The Union of India & Ors. (D.O.J. 08.09.2026)
Loading Viewer...






