Service Law: Test

The learned Single Judge had allowed the Writ Petition No. 29547 of 1997 filed by the respondent and quashed the order passed by the Appointing Authority and granted consequential benefits to the respondent. The Appointing Authority had, by its order of 31.01.1995, imposed a punishment of “reduction in basic pay to the lowest stage in Scale-I” as envisaged under Rule 49 (e) of the State Bank of India (Supervising Staff) Service Rules and further, has treated the period spent by the delinquent officer under suspension from 18.08.1990 till the date of his reinstatement as suspension only. (Para 1)

According to the learned counsel, the courts below have erred in characterizing the orders of the Disciplinary authorities as perverse. (Para 2)

Having considered the above, we are constrained to conclude that the charge of the Bank, that the inspection was not carried, stood established. Then it was for the respondent to show, as undertaken by him, what his response to the allegation was. (Para 22)

Here the specific charge was with regard to a series of named units, periodical inspections were not carried out. To support the charge, witnesses were examined and on the request through his defence representative, the Enquiry Officer has directed the presenting officer to produce the inspection records. (Para 24)

In view of the above, clearly with regard to the first limb of the first charge, namely, the failure to conduct periodical inspection, it cannot be said that the finding of the Enquiry Officer is on a mis-reading of the evidence or that the records of the inspection of units were part of the records that could be possibly misplaced or that a finding was based on some stray sentence and personal knowledge was imported by the Enquiry Officer de hors the record. Charge regarding formalities for creation of equitable mortgage (Para 25)

In the light of the above, the finding of the Enquiry Officer that the respondent, by his negligence, did not stipulate this in his recommendation to the Branch Manager and, as such, the advance could not be collaterally secured by creation of equitable mortgage cannot be said to be perverse or based on no evidence. (Para 30)

From the above discussion, it is clear that it could not be said that the Enquiry Report, the findings of the Disciplinary Authority and the order of the Appointing Authority are based on no evidence or are perverse. Even if we eschew the report insofar as the aspect of non-submission of control form, the transgression of the area of operation and non-declaration of the immovable property and certain other charges are concerned, the order of penalty can be sustained. (Para 32)

As has been demonstrated above, the aspects of failure to conduct periodic inspection and the negligence in not stipulating the taking of immovable property as collateral security in the case of M/s Saraswathi Fabricators in spite of the party offering it, constrain us to conclude that there was material on record for the appellant to pass the order of penalty. (Para 33)

It is now well settled that the scope of judicial review against a departmental enquiry proceeding is very limited. It is not in the nature of an appeal and a review on merits of the decision is not permissible. The scope of the enquiry is to examine whether the decision-making process is legitimate and to ensure that the findings are not bereft of any evidence. If the records reveal that the findings are based on some evidence, it is not the function of the court in a judicial review to re-appreciate the same and arrive at an independent finding on the evidence. This lakshman rekha has been recognized and reiterated in a long line of judgments of this Court. (Para 36)

In the present case, it could certainly not be said that the report is based on no evidence or that it is perverse. The learned Single Judge transgressed the limits of judicial review in setting aside the enquiry proceedings and the punishment imposed. The Division Bench, in a short order has, after extracting a part of the learned Single Judge’s judgment, gone on to hold that having perused the records of the enquiry they do not find that the charges have been dealt with in any manner of specificity. Thereafter they conclude that the learned Single Judge was justified in arriving at its conclusion. We are not able to sustain the orders of the learned Single Judge and the Division Bench. Severability of charges (Para 37)

The question that remains is, in the light of the findings above, does the order of penalty imposed call for any interference? (Para 38)

The law is well-settled that if in a disciplinary proceeding, the order of penalty can be imposed on the charges proved and the punishment imposed is lawfully sustainable on those charges, it is not for the Court to consider whether those grounds alone would have weighed with the authority in imposing the punishment. No doubt, on the facts of the present case, on some aspects of the charge, the proof may have been found wanting. (Para 39)

Then the only question is does the penalty imposed shock the conscience of the Court? In the oral arguments as well as in the written submissions, the respondent contended that there was no charge of financial misappropriation or of causing any financial loss to the Bank. This submission was countered by the appellant by placing reliance on the judgment of this Court in Disciplinary Authority-cum- Regional Manager and Others vs. Nikunja Bihari Patnaik, (1996) 9 SCC 69, particularly, the holding of the Court in para seven thereof to contend that the test is really not of loss having been resulted or profit having been made. The test is whether the delinquent employee, has observed the prescribed norms of the Bank. The penalty imposed in this case is “reduction in basic pay to the lowest stage in Scale-I” as envisaged under Rule 49 (e) of the State Bank of India (Supervising Staff) Service Rules and further, to treat the period spent by the delinquent officer under suspension from 18.08.1990 till the date of his reinstatement as suspension only. Since the charge of not conducting periodical inspection and the failure to complete the formalities for creating equitable mortgage with regard to M/s Saraswathi Fabricators are supported by evidence, we do not think that the penalty as imposed is disproportionate so as to shock the conscience of the Court. We maintain the penalty as imposed in the order of the Appointing Authority dated 31.01.1995 and as confirmed by the Appellate Authority. (Para 40)

SUPREME COURT OF INDIA

2023 STPL(Web) 211 SC

[2023 INSC 766]

State Bank Of India Vs. A.G.D. Reddy

Civil Appeal No. 11196 of 2011-Decided on 24-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-211-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles