SARFAESI: Forfeiture of earnest-money on default to deposit bid amount – Equity cannot supplant the law

(A) Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, Section 13(4), 35, 37–Security Interest (Enforcement) Rules, 2002, Rule 9(5) – Contract Act, 1872, Section 73, 74 – Secured Assets – Auction sale – Default to deposit bid amount – Forfeiture of earnestmoney deposit – Whether, the underlying principle of Section(s) 73 & 74 respectively of the 1872 Act is applicable to forfeiture of earnest-money deposit under Rule 9(5) of the SARFAESI Rules? In other words, whether the forfeiture of the earnest-money deposit under Rule 9(5) of the SARFAESI Rules can be only to the extent of loss or damages incurred by the Bank? – Held that the SARFAESI Act is a special legislation with an overriding effect on the general law, and only those legislations which are either specifically mentioned in Section 37 or deal with securitization will apply in addition to the SARFAESI Act – Being so, the underlying principle envisaged under Section(s) 73 & 74 of the 1872 Act which is a general law will have no application, when it comes to the SARFAESI Act more particularly the forfeiture of earnest-money deposit which has been statutorily provided under Rule 9(5) of the SARFAESI Rules as a consequence of the auction purchaser’s failure to deposit the balance amount. (Para 34, 68, 79)

(B) Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, Section 13(4), 35, 37 – Security Interest (Enforcement) Rules, 2002, Rule 9(5) – Contract Act, 1872, Section 73, 74 – SARFAESI – Auction sale – Default to deposit bid amount – Forfeiture of earnestmoney deposit – Whether, the forfeiture of the entire amount towards the earnest-money deposit under Rule 9(5) of the Rules amounts to unjust enrichment? – In other words, whether the quantum of forfeiture under the SARFAESI Rule is limited to the extent of debt owed? – Held that the concept of ‘Unjust Enrichment’ is a by-product of the doctrine of equity and it is an equally well settled cannon of law that equity always follows the law – In other words, equity cannot supplant the law, equity has to follow the law if the law is clear and unambiguous – The consequence of forfeiture of 25% of the deposit under Rule 9(5) of the SARFAESI Rules is a legal consequence that has been statutorily provided in the event of default in payment of the balance amount – The consequence envisaged under Rule 9(5) follows irrespective of whether a subsequent sale takes place at a higher price or not, and this forfeiture is not subject to any recovery already made or to the extent of the debt owed – In such cases, no extent of equity can either substitute or dilute the statutory consequence of forfeiture of 25% of deposit under Rule 9(5) of the SARFAESI Rules – Held that High Court erred in law by holding that forfeiture of the entire deposit under Rule 9 sub-rule (5) of the SARFAESI Rules by the appellant bank after having already recovered its dues from the subsequent sale amounts to unjust enrichment. (Para 109, 111 and 113)

(C) Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, Section 13(4), 35, 37 – Security Interest (Enforcement) Rules, 2002, Rule 9(5) – Contract Act, 1872, Section 73, 74 – SARFAESI – Auction sale – Default to deposit bid amount – Forfeiture of earnest-money deposit – Whether a case of exceptionable circumstances could be said to have been made out by the respondent to set aside the order of forfeiture of the earnest money deposit? – Respondent’s case that he was unable to make the balance payment owing to the advent of the demonetisation which led to a delay in raising the necessary finance – Held that the aforesaid by no stretch can be said to be an exceptional circumstance warranting judicial interference – Demonetization had occurred much before the e-auction was conducted by the appellant bank – As regards the requisition of documents, the sale was confirmed on 07.12.2016, and the respondent first requested for the documents only on 20.12.2016, and the said documents were provided to him by the appellant within a month’s time i.e., on 21.01.2017. – Respondent was granted an extension of 90-days’ time period to make the balance payment, and was specifically reminded that no further extension would be granted, in-spite of this the respondent failed to make the balance payment – The e-auction notice inviting bids along with the correspondence between the appellant bank and the respondent are unambiguous and clearly spelt out the consequences of not paying the balance amount within the specified period. – Respondent being aware of his financial capacity, willingly participated in the e-auction and offered his bid fully knowing the reserve price of the Secured Asset and the consequences of its failure in depositing the balance amount. (Para 118 to 121)

SUPREME COURT OF INDIA

2024 STPL(Web) 85 SC

[JT 2024 (2) SC 357 = 2024 INSC 80]

Authorised Officer, Central Bank Of India Vs. Shanmugavelu

Appeal No(S). 235-236 of 2024-Decided on 2-2-2024

https://stpllaw.in/wp-content/uploads/2024/04/2024-STPLWeb-85-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles