Environment Law: Issues decided were beyond the scope of appeal preferred before NGT

The Ministry of Environment, Forest and Climate Change of the Government of India granted environmental clearance (EC) to the appellant to develop the housing complex. On 18th April 2007, the Board granted CTE under the Air and Water Act. In 2013 and 2015, the appellant applied for renewal of the CTE. The applications were rejected. On 29th December 2015, the Board issued a show cause notice of closure under Section 33-A of the Water Act and Section 31-A of the Air Act. The notice also called upon the appellant to show cause why the appellant should not be penalised under the relevant provisions of the Air Act and the Water Act. The appellant replied to the said notice. (Para 1)

In January 2018, the appellant preferred an appeal before the Appellate Authority established under the Air and Water Acts by invoking Section 31 of the Air Act and Section 28 of the Water Act for setting aside the order dated 21st June 2017 passed by the Chairman of the Board granting approval to prosecute the appellant. The Appellate Authority, by judgment and order dated 15th March 2018, quashed the order of approval on the ground that, subsequently, ex-post facto CTE has been granted to the appellant. Being aggrieved by the said order of the Appellate Authority, the Board preferred an appeal under Section 16 of the National Green Tribunal Act, 2010, before the National Green Tribunal (NGT). By the impugned judgment, the appeal was allowed, and the order dated 15th March 2018 of the Appellate Authority was quashed and set aside. While doing so, in paragraph 12, observations were made by the NGT that EC granted on 29th August 2017 cannot condone the illegal construction raised from 9th April 2012 to 29th August 2017. NGT held that the environment clearance granted on 10th April 2007 expired on 9th April 2012. (Para 3)

He submitted that even assuming without admitting that the EC expired on 9th April 2012, renewal or grant of a fresh EC was not required as the superstructure of the building was complete before 9th April 2012, and for completing the further construction, EC was not required. In any event, EC was granted on 29th August 2017. The learned senior counsel urged that in any event, NGT had no reason to deal with the controversy regarding the effect of the absence of EC as the appeal was limited to the legality and validity of the order dated 15th March 2018 passed by the Appellate Authority. (Para 4)

Therefore, the only issue in the appeal preferred before the NGT was regarding the legality and validity of the order of the Appellate Authority and the approval granted on 21st June 2017 to prosecute the appellant. While dealing with the appeal, NGT ought not to have gone into the issue of whether the EC granted earlier expired on 9th April 2012. Considering the limited scope of appeal, NGT ought not to have gone into the question of whether the construction carried out by the appellant between 9th April 2012 to 29th August 2017 was illegal. Therefore, what is held in paragraph 12 of the impugned judgment will have to be set aside. (Para 7)

The said challenge at the instance of the appellant ought not to have been entertained by the Appellate Authority as the appellant was bound by condition no.4 in the ex-post facto CTE granted on 18th October 2017. In fact, the judgment of the Appellate Authority shows that the attention of the Appellate Authority was invited to the aforesaid condition no.4. After having acted upon the ex-post facto CTE dated 18th October 2017, the appellant cannot be allowed to approbate and reprobate. Therefore, interference by the Appellate Authority by its judgment dated 15th March 2018 was illegal and uncalled for. To that extent, the impugned judgment of the NGT cannot be interfered with. (Para 11)

The findings recorded in paragraph 12 of the impugned judgment are set aside on the ground that the issues decided thereunder were beyond the scope of appeal preferred before NGT. The issues which are dealt with in paragraph 12 are kept open. These issues can always be decided in appropriate proceedings in accordance with the law. All contentions on that behalf are left open; (Para 12(a))

SUPREME COURT OF INDIA

2023 STPL(Web) 427 SC

[2023 INSC 999]

M/S Sweta Vs. Estate Pvt.Ltd. Gurgaon Vs. Haryana State Pollution Control Board & Anr

Civil Appeal No. 2212 of 2020-Decided on 10-11-2023

https://stpllaw.in/wp-content/uploads/2023/11/2023-STPLWeb-427-SC.pdf

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Next Story

Executive instructions cannot nullify statutory rules

Assam Bonded Warehouse Rules, 1965 – Rule 7 – Refund of Charges – Administrative Order – Statutory Rules – The present writ petition contested an order issued by the Secretary to the Government of Assam, Excise Department, reintroducing establishment charges under Rule 7 of the Assam Bonded Warehouse Rules, 1965, despite their abolition by the Assam Bonded Warehouse (Amendment) Rules, 2005.

The Court held that executive instructions cannot nullify statutory rules. Citing the principle established in K. Kuppusamy case, it ruled that until a rule is amended, it remains applicable. Consequently, the impugned order was set aside as ultra vires. Regarding refund, relying on Mafatlal Industries Ltd. case, the Court directed the petitioner to present evidence to the Excise Commissioner, who would determine entitlement to refund within four months, considering whether the petitioner passed on the burden of charges to retailers. (Para 15)

GAUHATI HIGH COURT

2023 STPL(Web) 181 Gauhati

[2024 STPL 1649 Gauhati]

M/S Centenary Distilleries P Ltd. Vs. State Of Assam And 2 Ors.

WP(C) 2875 of 2014-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-181-Gauhati-2.pdf

 

Next Story

Land Disputes: Binding nature of Civil Court’s decree on Revenue Courts

Land Disputes – Binding nature of Civil Court’s decree on Revenue Courts – The instant writ petition challenged a judgment of the Assam Board of Revenue concerning a land dispute. The dispute pertained to a plot of land associated with the Dargah of Pir Saheb. The Civil Court in Title Suit No.176/1978 had decreed in favor of the Petitioners’ predecessor, declaring their right, title, and possession over the land. The State of Assam was restrained from interference. Subsequently, the Settlement Officer issued a Khatian in favor of the Petitioners’ predecessor, and a new Dag was created. However, the Assam Board of Revenue, in its impugned judgment, disregarded the Civil Court’s decree and cancelled the Khatian issued to the Petitioners’ predecessor.

This action was deemed contrary to established principles, as Civil Court decrees are binding on Revenue Courts. Therefore, the High Court set aside the impugned judgment, restoring the Khatian to the Petitioners’ predecessor. (Para 12)

GAUHATI HIGH COURT

2023 STPL(Web) 180 Gauhati

[2024 STPL 1648 Gauhati]

Sayed Moinuddin Ahmed Vs. State Of Assam And 3 Ors.

WP(C) 4701 of 2013-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-180-Gauhati.pdf

Recent Articles