Dacoity with Murder: Main witnesses wholly unreliable

Seven accused were convicted, including the present appellant-accused no.6, for the offences punishable under Section 396 read with Section 149, Section 395 read with Section 149, Section 307 read with Section 149, Section 435 read with Section 149 and Section 201 read with Section 149 of the Indian Penal Code, 1860 (Para 1)

Considering the nature of the testimony of PW2, it cannot be said that the evidence of PW2 is wholly reliable. The identification of the appellant for the first time in the Court after a lapse of about two years becomes doubtful for more than one reason. Firstly, the appellant was not known to PW2. Secondly, the appellant was part of a large aggressive mob of 50 to 100 people which surrounded the autorickshaw. Thirdly, there was no identification parade held. Fourthly, there was no time available to PW2 to note the distinctive features of the appellant. Hence, it is very unsafe to record a conclusion based only on the testimony of the solitary witness that the guilt of the appellant was proved beyond a reasonable doubt. (Para 8)

Now, coming to the role of accused nos.2,3 and 4, we must note here that the only role ascribed to them was that they were a part of the mob. No overt act was ascribed to them. The Trial Court believed the testimony of PW25 (Arifkhan) and PW26 (Sachinbhai Patel). Both PW25 and PW26 identified accused no.2. However, a test identification parade was not conducted. (Para 9)

As far as accused no.3 is concerned, he was identified by PW26 as a member of the mob. After having perused the testimony of PW25, we find that he has not specifically named accused no.3. Accused no.4 was not identified by PW26, but the finding of the Trial Court is that he was identified by PW25. (Para 10)

This Court was of the view that evidence of PW25 and PW26 does not inspire confidence. This Court did not partially reject the testimony of PW25 and PW26 but rejected their testimony in its entirety. (Para 12)

Accused nos. 1,5 and 13 were convicted only on the basis of the testimony of PW25 and PW26. They were acquitted by holding that the testimony of both witnesses was unreliable and deserved to be discarded. (Para 17)

SUPREME COURT OF INDIA

2023 STPL(Web) 265 SC

[2023 INSC 829]

Javed Shaukat Ali Qureshi Vs. State Of Gujarat

Criminal Appeal No. 1012 of 2022-Decided on 13-9-2023

https://stpllaw.in/wp-content/uploads/2023/09/2023-STPLWeb-265-SC.pdf

 

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles