Criminal: Transfer Petition – Cases already at final stage retransferred – Remaining cases to be heard by Transferee Court from the stage, it had received from the transferor Court

Primarily contested the application on the merits of the Transfer Petition and stated that the petition was filed by accused Ketan Kantilal Seth with an ulterior motive to derail and delay the trials which are pending against him since almost 20 years in different States. He further contended that, allowing of the Transfer Petition vide order dated 09.09.2022 has led to denovo trial of R.C.C. No. 147/2002 and in fact, this Court has effectively setaside the order dated 24.06.2021 passed by Bombay High Court in Criminal Application No. 628/2021 vide which the Trial Court was directed to conclude the trial in R.C.C. No. 147/2002 within specified time, wherein hearing stood concluded, though judgment was not pronounced by Trial Court in view of the order dated 13.05.2022 of this Court. While closing the arguments, the learned senior counsel submitted that such transfer of cases by this Court has effectually led to an adverse effect on the whole efforts of all the stakeholders involved who have been in pursuit of justice since more than 20 years. (Para 6)

Mr. Tushar Mehta, learned senior counsel appearing on behalf of State of Maharashtra, contested M.A. No. 1935/2022 and sought recall/modification of the order dated 09.09.2022 predominantly on the ground that no opportunity of hearing was given to the State on the date when the matter was finally heard and same amounts to violation of principles of natural justice. It was further contended that, had there being any opportunity given to the State, all the development of the proceedings in respective Courts would have been brought to the notice of this Court. Learned senior counsel also laid emphasis on the fact that in view of the directions issued in paragraph 13(e), the trials are required to be started from the stage of framing of charge. It is said that, as per order dated 13.05.2022 of this Court, arguments were heard in R.C.C. No. 147/2002 by 155II, Additional Chief Judicial Magistrate, First Class, Nagpur and only the judgment is to be pronounced. Therefore, it was prayed that the order dated 09.09.2022 may be modified to the extent by which denovo trial of that case may be avoided. (Para 7)

After hearing learned counsels for the parties, in our view the recall of the entire order as prayed for on the instance of the intervenor is not justified, in particular looking at the detailed discussion made in order dated 09.09.2022. Simultaneously, it cannot be ignored that State of Maharashtra has filed application asking modification of the order. Therefore, in view of the aforesaid, we refrain ourselves to recall the order on insistence of the intervenor and deem it appropriate to consider the prayer of the State of Maharashtra taking note of the submissions made in this respect. (Para 15)

In view of the foregoing discussion, these applications be treated as disposedoff modifying the order dated 09.09.2022 to the extent indicated herein below – I. The order dated 09.09.2022 passed in Transfer Petition (Criminal) Nos. 333348/ 2021 is hereby modified and maintained subject to –

I. Criminal proceedings relating to Respondent/Accused Nos. 20, 23, 25, 26, 30, 31, 32 and 34 pending before transferor Court at Amravati, if already transferred to transferee Court, shall be returned to the transferor Court and continue at the transferor Court from the stage as received; IB. The review petition filed by Respondent/Accused Nos. 20, 23, 25, 26, 30, 31, 32 and 34 bearing Diary No. 36121/2022 and titled as ‘Ghanshyam Lahaunji Mudgal and others Vs. Ketan Kantilal Seth and others’ is dismissed as infructuous in view of observations made in paragraph 19 herein.

II. The transfer of R.C.C. No. 147/2002 by order dated 09.09.2022 passed in Transfer Petition (Criminal) Nos. 333348/ 2021 is restrained to the transferor Court with a clarification that the trial shall proceed from the stage of final arguments by the Presiding Officer uninfluenced by the directions in para 13(e) of order dated 09.09.2022.

III. Directions issued in para 13(e) in order dated 09.09.2022 be now read as under – “On receiving the cases as mentioned in para 13(a), the transferee Court shall proceed in those cases from the stage of the case in which it had received from the transferor Court(s). The cases in which charges have not been framed, it shall be framed within two months and the trial shall start immediately. In cases in which charges have already been framed and evidence has been started after submitting the trial program, those cases shall proceed from that stage of trial. Meaning thereby, denovo trial in such cases from stage of framing of charge is not required. The transferee Court(s) shall conclude all the trials as expeditiously as possible within a period of two years.”

IV. Lastly, we make it clear that this Court vide order dated 09.09.2022 never intended or meant to setaside the order dated 24.06.2021 passed by Bombay High Court. It is clarified that the concerned trial Court at Nagpur shall make all the endeavor to comply with the timeline as given by Bombay High Court and decide the case in accordance with law. (Para 21)

SUPREME COURT JUDGMENT

Citation: 2023 STPL(Web) 135 SC

Ketan Kantilal Seth Vs. State of Gujarat And ors.

Miscellaneous Application No. of 2023 [D.No. 33197 of 2022] In Transfer Petition (Criminal) Nos. 333348/ 2021 With M.A. No. 1935 of 2022 In T.P. (Crl.) Nos . 333348 of 2021-Decided on 4-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-135-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles