This civil appeal challenged a judgment of the Meghalaya High Court, which had allowed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, and restored the pre-reference interest awarded by an Arbitral Tribunal to the respondent contractor. The Supreme Court allowed the appeal and set aside the High Court’s judgment to the extent it restored pre-reference interest. The Court drew a crucial distinction between the older Arbitration Act of 1940 and the 1996 Act, emphasizing that under Section 31(7) of the 1996 Act, party autonomy is paramount and an express contractual bar against interest overrides the tribunal’s power to award it. The Court held that Clause 54 of the General Conditions of Contract (GCC) in this case—which explicitly bars interest on money lying with the corporation due to a dispute or due to delay in making periodical/final payments—is distinguishable from the clause in State of U.P. v. Harish Chandra, and instead aligns with Sayeed Ahmed & Co., thus effectively operating as a complete bar on pre-reference interest.

  • Factual & Contractual Background: The appellant (NEEPCO) awarded a civil contract for a gas turbine power project to the respondent in 1996. Disputes regarding delay led to arbitration, resulting in an award granting a principal sum along with 12% pre-reference interest and 9% pendente lite/future interest.
  • Commercial Court vs. High Court: The Commercial Court set aside the pre-reference and pendente lite interest relying on Clause 54 of the GCC and Sayeed Ahmed & Co.. However, the High Court reversed this under Section 37, relying on Harish Chandra, concluding that Clause 54 only barred interest on withheld money due to a dispute, not on general delayed payments.
  • Statutory Regime Shift (1940 Act vs. 1996 Act): The Supreme Court detailed how the 1996 Act recalibrated the law through Section 31(7)(a), which explicitly subjects the arbitrator’s power to award interest to the phrase “unless otherwise agreed by the parties”. Unlike the 1940 Act (where a strict-construction approach required specific wording excluding the arbitrator), under the 1996 Act, an express contractual bar in the agreement suffices to exclude the power.
  • Interpretation of Clause 54: The Court analyzed Clause 54 and distinguished it from Harish Chandra. While Harish Chandra dealt only with money withheld due to a dispute, Clause 54 expressly added an independent limb barring claims for interest or damages with respect to any delay on the part of the engineer-in-charge in making periodical or final payments. This structural difference brings delayed payments squarely within the contractual prohibition.
  • Rejection of Waiver Argument: The Court dismissed the respondent’s contention that the appellant had waived its right to invoke Clause 54, noting that the plea was specifically raised in the statement of defence filed before the Arbitral Tribunal. Consequently, the award of pre-reference interest was set aside for exceeding the tribunal’s jurisdiction.

2026 INSC 1036

North Eastern Electric Power Corporation Limited (NEEPCO) v. Astra Construction Private Limited (D.O.J. 22.09.2026)

Loading Viewer...

Next Story

Custodial Torture Trial Transferred To Srinagar For Victim

The Supreme Court ordered the transfer of a CBI-investigated custodial torture criminal trial from the Principal Sessions Judge, Kupwara to the Principal District and Sessions Judge, Srinagar, holding that Article 21 fair-trial protections extend to victims and that the appellant—a police constable allegedly subjected to custodial brutality—should not face avoidable travel hardship or anxiety before accused personnel on bail. Setting aside the High Court’s March 25, 2026 refusal under Section 447 BNSS, the Court directed the Srinagar court to endeavor to conclude the trial within two years.

  • Background & CBI Investigation: The appellant, a police constable, was allegedly subjected to custodial torture in February 2023 requiring surgery at SKIMS Soura, Srinagar. Following earlier proceedings and a Supreme Court judgment dated July 21, 2025 transferring the probe to the CBI, the CBI registered an FIR on July 26, 2025 and filed a chargesheet against respondent Nos. 2 to 9 under Sections 120-B, 323, 325, 330, 331, and 343 IPC, with committal to the Sessions Judge, Kupwara on November 20, 2025.
  • High Court Refusal: The High Court of Jammu and Kashmir and Ladakh at Srinagar dismissed the appellant’s transfer petition under Section 447 BNSS on March 25, 2026.
  • Victim’s Right to Fair Trial Under Article 21: The Supreme Court held that the right to a fair trial under Article 21 protects victims as well as accused persons, noting the appellant’s physical and psychological trauma, prior struggle to secure an independent CBI investigation, travel burden between Kupwara and Srinagar, and anxiety of facing accused persons currently on bail.
  • Transfer & Trial Timeline: Setting aside the High Court’s order, the Court transferred the case (UT of J&K through SHO, P.S. CBI v. Aijaz Ahmad & Others) to the Principal District and Sessions Judge, Srinagar, urged completion of the trial within two years, and clarified that no observations touch upon the merits or guilt.

2026 INSC 1274

Khursheed Ahmad Chowhan vs. Union Territory of J and K & Ors. (D.O.J. 20.11.2026)

Loading Viewer...

Next Story

Wife Retains Maintenance Lands And Gets Higher Interim Pay

The Supreme Court held that a wife cannot be compelled to surrender possession of properties given under a maintenance arrangement at the stage of deciding an application for interim maintenance under Section 24 of the Hindu Marriage Act, 1955. Setting aside the Madras High Court’s July 12, 2024 order directing restoration of agricultural and tea-estate lands to the husband, the Court allowed the wife to retain possession and enhanced interim maintenance from Rs. 4,000 to Rs. 15,000 per month from the date of the order.

  • Background & Matrimonial Dispute: Following marital discord after their October 22, 2007 marriage and the birth of a daughter on February 21, 2009, an agreement dated December 8, 2011 placed a tea estate, agricultural parcels, and a portion of a residential house in the appellant-wife’s possession for maintenance of herself and their daughter. While the husband’s divorce petition under Section 13(1)(ia) of the Hindu Marriage Act, 1955 was pending, the wife sought interim maintenance under Section 24, resulting in a March 26, 2014 order awarding Rs. 4,000 per month and Rs. 10,000 litigation expenses.
  • High Court Revision Order: On July 12, 2024, the Madras High Court partly allowed the husband’s revision petition, ordering the wife to hand over possession of the tea estate and agricultural lands while retaining the residential house, directing payment of Rs. 1,50,000 towards past maintenance, and continuing Rs. 4,000 per month future maintenance upon surrender of the agricultural properties.
  • Retention of Properties & Enhanced Maintenance: The Supreme Court ruled that the interim nature of the 2011 arrangement or the husband’s willingness to pay maintenance upon return of possession did not justify dispossessing the wife at the interim maintenance stage without assessing actual net income, cultivation expenses, and management ability. Noting that Rs. 4,000 per month had remained unchanged for over twelve years and that the daughter—now over seventeen years old—was being raised solely by the mother, the Court raised interim maintenance to Rs. 15,000 per month prospectively while preserving the Rs. 1,50,000 past maintenance direction (subject to adjustments) to be cleared within eight weeks.
  • Clarification on Merits: The Court clarified that its directions govern only interim maintenance and leave all substantive property rights and matrimonial issues open for independent adjudication.

2026 INSC 1273

B. Prema vs. B. Rajkumar (D.O.J. 25.11.2026)

Loading Viewer...

Next Story

Act Only Policy Scope And Article 142 Pay-And-Recover Power

The Supreme Court held that compulsory third-party insurance under Section 147 of the Motor Vehicles Act, 1988 does not automatically cover gratuitous occupants of a private vehicle or pillion riders on a two-wheeler under an “Act Only” policy where no additional premium was paid. However, affirming the insurer’s non-liability, the Court exercised its extraordinary power under Article 142 of the Constitution to direct the insurer to first satisfy the outstanding compensation award and recover it from the vehicle owner, setting out four cumulative requirements for such relief.

  • Accident, Claim & High Court Ruling: Following a fatal accident on April 15, 2012 involving a Tata Sumo jeep driven by its owner (Abdul Gazi) in which occupant Suryakant Pandurang Nikam died, the Motor Accident Claims Tribunal awarded Rs. 7,79,800 with 7.5% interest and ordered “pay and recover” against United India Insurance Company Ltd., finding policy breach/no passenger coverage. The Bombay High Court (Aurangabad Bench) exonerated the insurer on August 5, 2019, holding that an Act Only Policy did not cover a private-car occupant and that Tribunals/High Courts lack Article 142 powers.
  • Compulsory Coverage Under Section 147: Interpreting Sections 145(g), 146, 147, and 149 of the MV Act alongside precedents such as Asha Rani, Baljit Kaur, Tilak Singh, Sudhakaran K.V., and Balakrishnan, the Court ruled that being a person other than the insured or insurer does not automatically bring an occupant or pillion rider within compulsory Act Only coverage. Coverage depends on the statutory scheme and the specific risks undertaken in the policy.
  • Article 142 Framework for Pay and Recover: Examining Supreme Court Bar Association, Shilpa Sailesh, and earlier pay-and-recover decisions, the Court held that absence of statutory/contractual liability is not an absolute bar to Supreme Court intervention under Article 142 (a power belonging to the Supreme Court alone, not Tribunals or High Courts). Exceptional pay-and-recover relief requires satisfying four cumulative criteria: (i) established, judicially determined liability; (ii) exceptional necessity to prevent substantial injustice; (iii) necessity and proportionality; and (iv) procedural fairness with effective recovery safeguards.
  • Application & Operative Directions: Considering the judicially determined liability against the owner, over fourteen years elapsed since the 2012 accident, and the elderly widow appellant’s financial and medical hardship, the Court directed the insurer to deposit the verified unpaid compensation and interest within eight weeks of the Tribunal’s four-week determination, and recover it from the owner through execution proceedings before the Tribunal without filing a separate suit.

2026 INSC 1272

Sukumarbai & Ors. vs. United India Insurance Company Ltd. & Anr. (D.O.J. 25.11.2026)

Loading Viewer...

Next Story

Eligibility Alone Cannot Confer Absorption Without A Sanctioned Post

The Supreme Court held that acquiring academic eligibility on a given date does not entitle a lecturer appointed on an unsanctioned post to retrospective absorption from that eligibility date when no sanctioned or pre-cut-off recommended post was available. Affirming the Division Bench of the Jharkhand High Court, the Court upheld the appellant’s absorption with effect from June 1, 2003—when a sanctioned post fell vacant upon retirement—as approved by the Justice S.B. Sinha Commission.

  • Background & Appointments: The appellant was appointed on February 22, 1986 as a Lecturer in Hindi on a fifth post at S.J.S.N. College, Garhwa, without possessing the requisite minimum qualification on that date, which he acquired on December 5, 1987. Four senior lecturers were already working against the four sanctioned posts in Hindi, while the University’s forwarding of the college’s proposal for additional posts (5th to 8th) occurred on July 11, 1987, after the March 31, 1987 cut-off date.
  • Commission Reports & Absorption Order: Following the Justice S.C. Agrawal Commission report (accepted by the Supreme Court in State of Bihar v. Bihar Rajya MSESKK Mahasangh) and subsequent individual scrutiny by the Justice S.B. Sinha Commission, the appellant’s absorption was upheld with effect from June 1, 2003 following the retirement of lecturer Ram Naresh Pathak on May 31, 2003.
  • Single Judge vs. Division Bench: A Single Judge of the Jharkhand High Court allowed the appellant’s writ petition and directed consideration of absorption from December 5, 1987 based on his listing in Annexure IV-A of the Agrawal Commission report. On Letters Patent Appeal, the Division Bench set aside the Single Judge’s order, holding that eligibility without a sanctioned post before the cut-off date conferred no right to earlier absorption.
  • Supreme Court Ruling: The Supreme Court ruled that Annexure IV-A only lists teachers eligible to be considered for absorption according to eligibility dates and cannot create a right where no sanctioned or timely recommended post existed. Noting also that the Justice Sinha Commission found the relied-upon letter not genuine and properly recognized absorption against a subsequent superannuation vacancy, the Court dismissed the appeal.

2026 INSC 1271

Brij Kumar Mishra vs. Nilamber Pitambar University & Ors. (D.O.J. 25.11.2026)

Loading Viewer...

Recent Articles