Condonation of Delay: Appeal was filed beyond the period of thirty days, it was within the condonable period of fifteen days

At the outset, it is clarified that the findings in this judgement are limited to a determination of the question of limitation. The detailed facts and averments on the merits of the larger dispute between the parties are not analysed in the judgment. (Para 3)

From the above discussion of law, It is clear that the date on which the limitation begins to run is intrinsically linked to the date of pronouncement. The question that arises in the facts of the present case, therefore, is when is an order deemed to be pronounced. The National Company Law Tribunal Rules, 2016[“NCLT Rules”] provide guidance in this regard. Rule 89(1) of the NCLT Rules indicates that when NCLAT registry publishes its cause list, a distinction is drawn between cases listed for pronouncement of orders and other cases. It states as follows (Para 16)

The above provisions of the NCLT Rules, 2016 make a clear distinction between the ‘hearing’ of an appeal and the ‘pronouncement’ of the order. Rule 150(1) provides that after hearing the parties, the order may be pronounced either at once or soon thereafter, as may be practicable, but not later than thirty days from the final hearing. Further, Rule 151 indicates that a member of the bench may pronounce the order for and on behalf of the Bench. When the order is pronounced, the court master shall make a note in the order sheet to that effect. The language of the above rules indicates that the pronouncement of the order is necessary and cannot be dispensed with. (Para 18)

In the facts of the present case, the date of upload of the order is the same as the date of pronouncement. To avoid situations such as these, in cases where the matter has been heard on a particular day but the order is pronounced on a later date, the NCLT must refrain from affixing the date of hearing on the order. Such an approach would be a violation of the NCLT Rules, which create a distinction between hearing and pronouncement and do not allow the NCLT to dispense with the requirement of pronouncement. (Para 20)

In view of the above, the period of limitation began to run on 30 May 2023. The 30- day limitation period provided in Section 61(2) of the IBC concluded on 29 June 2023. Though the appeal was filed beyond the period of thirty days, it was within the condonable period of fifteen days. We are of the considered view that the appeal should be restored to the NCLAT for reconsidering whether the appellant has shown sufficient cause for condoning the delay beyond thirty days. To facilitate this, the impugned order of the NCLAT declining to condone the delay is set aside and the proceedings are restored to the file of the NCLAT. We are not inclined to stay the CIRP at this stage. However, the NCLAT is directed to dispose of the appeal at the earliest. (Para 21)

SUPREME COURT OF INDIA

2023 STPL(Web) 485 SC

[2023 INSC 1063]

Sanjay Pandurang Kalate Vs. Vistra Itcl (India) Limited And Others

Civil Appeal Nos. 7467-7468 of 2023-Decided on 4-12-2023

https://stpllaw.in/wp-content/uploads/2024/01/2023-STPLWeb-485-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles