Arbitration: Rejection of claims valid

This appeal arises out of the decision of the Division Bench of the High Court of Bombay under Section 37 of the Arbitration and Conciliation Act 1996 (Para 1)

Rejecting all claims were set aside and certain claims were allowed. This appeal by Konkan Railway Corporation Limited challenges the legality of the order passed by the Division Bench of the High Court while exercising jurisdiction under Section 37 of the Act. (Para 1)

The Arbitral Tribunal by its award dated 15.11.2014 considered the three disputes and rejected all the claims. (Para 4)

The contract in favour of the Respondent was entered into on 24.11.2004. At that time the Notification of the Government of Jammu and Kashmir dated 19.12.2003 exempted Entry Tax on earth-moving instruments. However, during the execution of the contract, on 25.01.2008, the Government of Jammu and Kashmir withdrew the exemption notification. Consequently, the Respondent raised claims for reimbursement of Rs. 1,32,29,771/- incurred on account of payment of Entry Tax. (Para 5)

In so far as Dispute IV is concerned, it relates to reimbursement of Toll Tax on machinery and materials. As per the extant policy in Jammu and Kashmir, the Toll Tax as applicable on the date of the submission of tender, that is 31.05.2004, was Rs. 400/- per MT. However, through four subsequent notifications issued under Jammu and Kashmir Levy of Toll Tax Act, 1998, the taxes were progressively increased to Rs. 650/- per MT. Consequently, the Respondent raised a claim of Rs. 5,23,279/-, incurred on account of increase in toll tax during the subsistence of the contract. (Para 6)

The Arbitral Tribunal was of the view that Entry Taxes on earth-moving equipment formed part of the cost of the works quoted in the Bill of Quantities. For this reason, the Arbitral Tribunal came to the conclusion that the increased liability on account of imposition of Entry Tax could not be reimbursed under Clause 5.1.2, as recoupment for the same could only be governed by the Price Variation clauses (clause 7.1.1 and 7.1.2 in Chapter 7). (Para 8)

The Tribunal reasoned that the contractor was aware of these conditions at the time when the prices were quoted, and therefore, the claim could not succeed under Price Variation clauses. (Para 8.2)

As regards the claim for Toll Tax which formed part of Dispute IV, the Tribunal adopted the same interpretation of the contractual clauses and rejected the claim. (Para 8.3)

It finally concluded that the approach adopted by the Arbitral Tribunal would amount to perversity, and therefore, found it necessary to set aside the Award, and allow claims covered under Disputes III and IV. (Para 10)

This judgment of the Division Bench of the Hight Court led to the present civil appeal before us. (Para 11)

In the present case, the Arbitral Tribunal interpreted the contractual clauses and rejected the Respondent’s claims pertaining to Disputes I, III and IV. The findings were affirmed by the Single Judge of the High Court in a challenge under Section 34 of the Act, who concluded that the interpretation of the Arbitral Tribunal was clearly a possible view, that was reasonable and fair-minded in approach. (Para 16)

In the present case, we have examined the appreciation of evidence by the Arbitral Tribunal as well as the Single Judge of the High Court. We are convinced that their appreciation of the facts and interpretation of the contract is reasonable, and comprises a possible view. Keeping in mind the mandate of Section 5 of the Act 1996, [Arbitration and Conciliation Act, 1996, section 5: (Para 22)

we are of the opinion that the Division Bench of the High Court committed an error in setting aside the concurrent findings of the Arbitral Tribunal and the Single Judge of the High Court. The Award of the Arbitral Tribunal and the decision of the Single Judge of the High Court under Section 34 of the Act cannot be termed as perverse or patently illegal as concluded by the Division Bench of the High Court. The decision of the Arbitral Tribunal is a plausible view, and the Single Judge refrained from interfering with it under Section 34 of the Act. We are of the opinion that the Division Bench should not have interfered with these orders. (Para 24)

SUPREME COURT OF INDIA

2023 STPL(Web) 184

[2023INSC742]

Konkan Railway Corporation Limited Vs. Chenab Bridge Project Undertaking

Civil Appeal No. 2903 of 2023 (Arising out of S.L.P. (C) No. 5640 of 2023)-Decided on 17-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-184-SC.pdf

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Next Story

Executive instructions cannot nullify statutory rules

Assam Bonded Warehouse Rules, 1965 – Rule 7 – Refund of Charges – Administrative Order – Statutory Rules – The present writ petition contested an order issued by the Secretary to the Government of Assam, Excise Department, reintroducing establishment charges under Rule 7 of the Assam Bonded Warehouse Rules, 1965, despite their abolition by the Assam Bonded Warehouse (Amendment) Rules, 2005.

The Court held that executive instructions cannot nullify statutory rules. Citing the principle established in K. Kuppusamy case, it ruled that until a rule is amended, it remains applicable. Consequently, the impugned order was set aside as ultra vires. Regarding refund, relying on Mafatlal Industries Ltd. case, the Court directed the petitioner to present evidence to the Excise Commissioner, who would determine entitlement to refund within four months, considering whether the petitioner passed on the burden of charges to retailers. (Para 15)

GAUHATI HIGH COURT

2023 STPL(Web) 181 Gauhati

[2024 STPL 1649 Gauhati]

M/S Centenary Distilleries P Ltd. Vs. State Of Assam And 2 Ors.

WP(C) 2875 of 2014-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-181-Gauhati-2.pdf

 

Next Story

Land Disputes: Binding nature of Civil Court’s decree on Revenue Courts

Land Disputes – Binding nature of Civil Court’s decree on Revenue Courts – The instant writ petition challenged a judgment of the Assam Board of Revenue concerning a land dispute. The dispute pertained to a plot of land associated with the Dargah of Pir Saheb. The Civil Court in Title Suit No.176/1978 had decreed in favor of the Petitioners’ predecessor, declaring their right, title, and possession over the land. The State of Assam was restrained from interference. Subsequently, the Settlement Officer issued a Khatian in favor of the Petitioners’ predecessor, and a new Dag was created. However, the Assam Board of Revenue, in its impugned judgment, disregarded the Civil Court’s decree and cancelled the Khatian issued to the Petitioners’ predecessor.

This action was deemed contrary to established principles, as Civil Court decrees are binding on Revenue Courts. Therefore, the High Court set aside the impugned judgment, restoring the Khatian to the Petitioners’ predecessor. (Para 12)

GAUHATI HIGH COURT

2023 STPL(Web) 180 Gauhati

[2024 STPL 1648 Gauhati]

Sayed Moinuddin Ahmed Vs. State Of Assam And 3 Ors.

WP(C) 4701 of 2013-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-180-Gauhati.pdf

Recent Articles