Arbitration: Basic document has arbitration clause- No need for arbitration clause in subsequent documents

The only question to be decided by us here is whether the Trial Court and the High Court have rightly referred the matter to arbitration or the dispute is of such a nature that it is not liable to be referred to arbitration, as there was no arbitration clause in the Conveyance Deed dated 17.12.2019 or if there was, yet the matter in any case is such that it is not arbitrable. (Para 2)

In the present case, the 2007 as well as the 2008 Tripartite Agreement, forms the basis for all subsequent agreements, conveyance, etc. The arbitration clause is also very wide in its scope, as we have already seen. At the sake of repetition, the 2008 Tripartite Agreement states that “any dispute, in relation to these agreements or in relation to any matter touching or arising from this Agreement, shall be referred to arbitration. (Para 8)

The contention of the appellants therefore that the dispute raised in the civil suit is non- arbitrable is also not correct. The dispute relates to a property which is the subject matter of the two tripartite agreements dated 31.03.2007 and 25.07.2008. (Para 8)

In the present case there are broadly three objections of the appellants on the Section 8 application moved by the respondents which has already been allowed by the two courts below. The first objection regarding the absence of an arbitration clause in the Conveyance Deed dated 17.12.2019 and the development agreements has already been discussed in detail in the preceding paragraphs. (Para 18)

The second is that the suit filed by the appellants is for cancellation of a document relating to immovable property i.e. land and it therefore amounts to an action in rem and hence arbitration is not the remedy. This question however, is no more res integra. Elaborate analysis on this aspect has been done by this Court in the case of Deccan Paper Mills v. Regency Mahavir Properties, (2021) 4 SCC 786, therein this court after referring to all the relevant precedents and the case laws has held that whether it is a suit for cancellation of a deed or a declaration of rights rising from the deed, it would only be an action in personam and not in rem. The decision of the Division Bench of Andhra Pradesh High Court in Aliens Developers (P) Ltd. v. Janardhan Reddy, 2015 SCC Online Hyd 370, was held to be wrong wherein it was held that a suit under Section 31 of Specific Relief Act amounts to an action in rem and this adjudicatory function can only be done by the Competent Civil Court and the powers cannot be exercised by an Arbitrator. The basic foundation of the Court for holding that a Section 31 suit for cancellation of a document amounts to an action in rem was held to be wrong. The entire scope and ambit of the Specific Relief Act, 1963 was considered and in Deccan Paper Mills (supra), the anomalies in law for holding such to be an action in rem were discussed and it was held that a relief sought under the Specific Relief Act is nothing but an action in personam. (Para 19)

The third objection is regarding fraud. The plea of fraud raised by the appellants in their objection to the Section 8 application has never been substantiated. Except for making a bald allegation of fraud there is nothing else. This Court has consistently held that a plea of fraud must be serious in nature in order to oust the jurisdiction of an Arbitrator. In Rashid Raza v. Sadaf Akhtar, (2019) 8 SCC 710, this Court laid down two conditions which must be satisfied before the Court can refuse to refer the matter to the Arbitrator, a forum consciously decided by parties in an agreement. The first is whether the plea permeates the entire contract and above all, the arbitration agreement, rendering it void or secondly, whether the allegation of fraud touches upon the internal affairs of the parties inter se having no implication in the public domain. The allegations must have some implication in public domain to oust the jurisdiction of an Arbitrator, if an allegation of fraud exists strictly between the parties concerned, the same will not be termed to be as a serious nature of fraud and hence would not be barred for arbitration. (Para 20)

SUPREME COURT OF INDIA

2023 STPL(Web) 489 SC

[2023 INSC 1081]

Sushma Shivkumar Daga & Anr. Vs. Madhurkumar Ramkrishnaji Bajaj & Ors.

Civil Appeal No. 1854 of 2023-Decided on 15-12-2023

https://stpllaw.in/wp-content/uploads/2024/01/2023-STPLWeb-489-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles