Service Law – Promotion – Corruption case – Grievance of the petitioners that persons junior to the petitioners have been promoted to the post of Assistant Engineer, but their cases were not considered only for the reason that prosecution sanction has been granted against them, though there is no dispute that the petitioners are not named as accused persons in the charge-sheet and put up for trial. The petitioners were shown only as witnesses and, therefore, the department could not have deprived the petitioners from being considered for promotion to the next higher post of Assistant Engineer.
Held: Under the circumstances, this Court is of the considered view that non-consideration of the claims for promotion to the next higher post as well as grant of ACPS and MACPS as claimed by the petitioners is unjustified and the same are contrary to the provisions of law. The respondents are directed to place the cases of the petitioners before the review DPC, which is to be constituted within a period of four weeks from the date of receipt of a certified copy of this order. The review DPC will, thereafter, pass appropriate orders within a further period of two weeks therefrom. (Para 12, 35, 37)
GAUHATI HIGH COURT
2023 STPL(Web) 145 Gauhati
[GAHC010124462020]
Sri Dhruba Bharali Vs. State Of Assam
Writ Petition (C) NO. 3674 of 2020-Decided on 5-10-2023
https://stpllaw.in/wp-content/uploads/2023/10/2023-STPLWeb-145-Gauhati.pdf