Arbitration agreement not valid: High Court to determine dispute

The Division Bench has dismissed a Writ Appeal and thereby affirmed the correctness of an order dated 27 February 2018 of a Single Judge dismissing the writ petition filed by the appellant. (Para 2)

For the continuous supply of water at concessional rates for the operation of the factory. The agreement was valid for a period of 20 years from the commencement of production. On 3 April 1987 (Para 3)

The tariff for the supply of water for industrial use was fixed at Rs 18.40 per kL and Rs 9.20 per kL for non-domestic use. Between 6 June 2014 and 16 September 2014, water bills were raised on the appellant based on the tariff fixed in the agreements dated 11 November 2011. (Para 4)

A demand notice was received by the appellant from the Assistant Executive Engineer by which new water rates were sought to be implemented and the appellant was called upon to pay the differential amount with effect from 20 July 2011 till 30 June 2014. (Para 5)

The notice stated that the Board’s failure to pay HESCOM its dues would impact upon electricity and water supply. Citing losses caused to the Board, and the audit officers’ objections against the non-revision of water bills under government orders, the notice requested payment of arrears, in accordance with the revised rates. (Para 6)

The Writ Petition was dismissed by the Single Judge primarily on the ground that Clause 11 of the agreements stipulated that any dispute that would arise between the parties would be resolved firstly by mutual discussion and on a failure of the process, by referring the matter to the Chief Engineer, the second respondent, whose decision would be final and binding. The Single Judge also observed that in terms of clause 4 of the agreements, the Board was entitled to increase the rates. However, in view of the dispute resolution mechanism provided in Clause 11, the Single Judge declined to entertain the petition and relegated the petitioner to the contractual remedy in terms of the agreement. (Para 9)

Hence, the Division Bench held that the dispute arising out of the impugned notices was covered by the scope of the agreement, and no interference under Article 226 of the Constitution of India was warranted. (Para 10)

Whether the High Court was justified in dismissing the Writ Petition and the Writ Appeal on the strength of Clause 11 of the agreements between the parties. We must examine whether there was a valid arbitration agreement between the parties, justifying the referral to the Chief Engineer under Clause 11. (Para 14)

Once we have come to the conclusion that the provisions of Clause 11 do not constitute an arbitration agreement, the corollary is that the High Court ought not to have relegated the parties to the Chief Engineer on the strength of Clause 11. It would have been appropriate if the High Court had finally determined the challenge addressed by the appellant in the writ proceedings under Section 226 of the Constitution. Though the Single Judge has adverted to Clause 4, evidently there is no final determination in that regard. (Para 24)

The Court has been apprised of the fact that in the meantime, the appellant, which has been taken over by the Aditya Birla Group, has continued to pay the revised water rates and has cleared the arrears while reserving its rights to avail of the remedies. The appellant shall continue to pay the rates as fixed by the Board from time to time subject to such final orders as may be passed by the High Court in the Writ Petition which is restored to the file of the High Court. (Para 28)

2023 STPL(Web) 384 SC

[2023 INSC 916]

Supreme Court Of India

Solaris Chem Tech Industries Ltd. Vs. Assistant Executive Engineer Karnataka Urban Water Supply And Drainage Board & Anr.

Civil Appeal No 6609 of 2023 (Arising out of SLP (C) No 21920 of 2018)-Decided on 10-10-2023

https://stpllaw.in/wp-content/uploads/2023/10/2023-STPLWeb-384-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles