Electricity: Determination of Tariff

The appeals before the Appellate Tribunal arose out of the orders fixing tariffs passed by the Orissa Electricity Regulatory Commission (for short, ‘the Commission’) (Para 1)

The Commission is required to pass orders determining the annual revenue requirements (ARR) of various licensees. In fact, under Section 26(4) of the Orissa State Electricity Reforms Act, 1995, every licensee is required to provide to the Commission, full details of calculations of aggregate revenue likely to be earned during the ensuing financial year. While deciding the tariff, the Commission has to seek guidance from the principles incorporated in Section 61 of the Electricity Act. (Para 1)

In this group of appeals, Civil Appeal No.414 of 2007 has been preferred by GRIDCO for challenging the order dated 13th December 2006 of the Appellate Tribunal dealing with the order of the Commission dated 23rd March 2006 by which the annual revenue requirement (ARR) and bulk supply tariff (BST) for the financial year 2006-2007 of GRIDCO was finalised. The said order was passed on the application made by GRIDCO to the Commission. (Para 4)

The next category of appeals relates to ARR and Transmission Tariff orders (TT) for the financial years 2006- 2007 and 2007-2008 in respect of OPTCL. Civil Appeal No.417 of 2007 has been preferred by OPTCL, where the challenge is to the order dated 13th December 2006 passed by the Appellate Tribunal arising out of the order dated 23rd March 2006 of the Commission for the financial year 2006-2007 in respect of ARR and TT of OPTCL. WESCO, NESCO and SESCO (DISCOMS) have preferred Civil Appeal Nos.2939-2941 of 2011 for challenging the order dated 8th November 2010 passed by the Appellate Tribunal concerning the order dated 22nd March 2007 of the Commission in respect of ARR and TT of OPTCL for the financial year 2007-2008. (Para 8)

The third category of appeals arises out of the determination of ARR and retail supply tariff orders (RST) of DISCOMS and true-up orders. Civil Appeal No.759 of 2007 has been filed by the Commission for challenging the order dated 13th December 2006 passed by the Appellate Tribunal arising out of the order dated 23rd March 2006 passed by the Commission in respect of ARR and RST of DISCOMS for the financial year 2006-2007. Civil Appeal Nos.3595-3597 of 2011 are again preferred by the Commission for challenging the order dated 8th November 2010 passed by the Appellate Tribunal arising out of the order of the Commission dated 23rd March 2007 in respect of ARR and RST of DISCOMS for the financial year 2007-2008. The Commission passed the orders on the basis of the application made by DISCOMS. (Para 9)

However, in subsequent orders for subsequent years, the Appellate Tribunal held that the interest payable on the loan, being the cost, may be allowed to pass through. We have confirmed the view while dealing with the other impugned orders. The interest cannot be equated with the principal loan amount, as the interest will amount to the cost incurred by GRIDCO. However, the interest burden can be passed on to DISCOMS in proportion of their outstandings. Therefore, while passing a fresh order in terms of the final order, the Commission will have to allow the interest on the loan to pass through, as observed above, but the principal loan amount cannot be allowed to pass through. (Para 29)

We may note here that while passing an order pursuant to the order of remand, all the contentions based on the findings of the Appellate Tribunal and the Commission for subsequent years, as approved by this Court, must be taken into consideration by the Commission. If, in subsequent orders as approved by this Court, different criteria or different principle was applied, submissions based on the same can always be canvassed in the proceedings pursuant to the order of remand. (Para 34)

This appeal is preferred by M/s. Orissa Power Transport Corporation Limited (OPTCL). The issue concerns TT and ARR of OPTCL for the financial year 2006-2007. The three DISCOMS challenged the order of the Commission. The first issue was regarding the Commission allowing the advance against depreciation. The Appellate Tribunal held that the National Tariff Policy published by the Government of India on 16th January 2006 under Section 3 of the Electricity Act does not permit allowing advance against depreciation. Under clause (i) of Section 61 of the Electricity Act, the Commission has to be guided by the National Tariff Policy. Therefore, the Appellate Tribunal rightly held that what is not permissible, per the National Tariff Policy, cannot be allowed by the Commission. However, the finding of the Appellate Tribunal on this issue for the subsequent financial year 2007-2008 is to the contrary, which we have approved while deciding Civil Appeal nos.2339-2341 of 2011. Hence, the said finding requires interference. Hence, we restore the order of the Commission on this aspect. (Para 40)

The net result of the aforesaid discussion is as under:

i. The order impugned in Civil Appeal no.414 of 2007 is modified as stated in paragraphs 29 and 34 above. This appeal, only to that extent, is partly allowed;

ii. The order impugned in Civil Appeal no.417 of 2007 is modified in terms of paragraph 40 above. This appeal is partly allowed only to the above extent;

iii. The rest of the appeals are dismissed;

iv. The Commission shall proceed to implement the impugned orders of the Appellate Tribunal as modified above; and

v. The Commission shall pass consequential and incidental orders in accordance with law.

SUPREME COURT OF INDIA

2023 STPL(Web) 309 SC

[2023 INSC 872]

Gridco Ltd. Vs. Western Electricity Supply Company Of Orissa Ltd. & Ors. Etc.

Civil Appeal No. 414 of 2007 with Civil Appeal Nos.417 of 2007 & 759 of 2007 Civil Appeal Nos. 463 & 572 of 2011 Civil Appeal Nos.2939-41, 2942-43 of 2011 Civil Appeal Nos.3595-97 of 2011 Civil Appeal No.2674 of 2013 Civil Appeal Nos.10251-63 of 2013 Civil Appeal Nos.2625-38 of 2014 Civil Appeal Nos.3858-60 of 2014 Civil Appeal Nos.1380-82 of 2015 Civil Appeal Nos.8037-39 of 2015-Decided on 5-10-2023

https://stpllaw.in/wp-content/uploads/2023/10/2023-STPLWeb-309-SC.pdf

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Next Story

Executive instructions cannot nullify statutory rules

Assam Bonded Warehouse Rules, 1965 – Rule 7 – Refund of Charges – Administrative Order – Statutory Rules – The present writ petition contested an order issued by the Secretary to the Government of Assam, Excise Department, reintroducing establishment charges under Rule 7 of the Assam Bonded Warehouse Rules, 1965, despite their abolition by the Assam Bonded Warehouse (Amendment) Rules, 2005.

The Court held that executive instructions cannot nullify statutory rules. Citing the principle established in K. Kuppusamy case, it ruled that until a rule is amended, it remains applicable. Consequently, the impugned order was set aside as ultra vires. Regarding refund, relying on Mafatlal Industries Ltd. case, the Court directed the petitioner to present evidence to the Excise Commissioner, who would determine entitlement to refund within four months, considering whether the petitioner passed on the burden of charges to retailers. (Para 15)

GAUHATI HIGH COURT

2023 STPL(Web) 181 Gauhati

[2024 STPL 1649 Gauhati]

M/S Centenary Distilleries P Ltd. Vs. State Of Assam And 2 Ors.

WP(C) 2875 of 2014-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-181-Gauhati-2.pdf

 

Next Story

Land Disputes: Binding nature of Civil Court’s decree on Revenue Courts

Land Disputes – Binding nature of Civil Court’s decree on Revenue Courts – The instant writ petition challenged a judgment of the Assam Board of Revenue concerning a land dispute. The dispute pertained to a plot of land associated with the Dargah of Pir Saheb. The Civil Court in Title Suit No.176/1978 had decreed in favor of the Petitioners’ predecessor, declaring their right, title, and possession over the land. The State of Assam was restrained from interference. Subsequently, the Settlement Officer issued a Khatian in favor of the Petitioners’ predecessor, and a new Dag was created. However, the Assam Board of Revenue, in its impugned judgment, disregarded the Civil Court’s decree and cancelled the Khatian issued to the Petitioners’ predecessor.

This action was deemed contrary to established principles, as Civil Court decrees are binding on Revenue Courts. Therefore, the High Court set aside the impugned judgment, restoring the Khatian to the Petitioners’ predecessor. (Para 12)

GAUHATI HIGH COURT

2023 STPL(Web) 180 Gauhati

[2024 STPL 1648 Gauhati]

Sayed Moinuddin Ahmed Vs. State Of Assam And 3 Ors.

WP(C) 4701 of 2013-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-180-Gauhati.pdf

Recent Articles