Arbitration: Dissenting opinion cannot be treated as an award

The disputes in the present case culminated in a reference to the arbitration of three technical persons, who after considering the rival viewpoints and the materials before them, made the award[Award dated 30.03.2010]. The award was unanimous on most questions while, on others, there was a dissenting view of one of the arbitrators. (Para 2)

The single judge was of the considered opinion that as far as measurement aspects were concerned, the tribunal’s majority opinion reflected a plausible and reasonable view that did not call for interference (Para 3)

NHAI appealed to the Division Bench, which set aside the decision of the learned single judge, and held that the tribunal’s majority view, and award, were based on an implausible interpretation of the contract. (Para 4)

It is quite evident that in most cases, the view of DRPs and tribunals, and in two cases, majority awards of tribunals, favoured the arguments of contractors, that composite embankment construction took place, as a result of which measurement was to be done in a composite, or unified manner. Dissenting or minority views, wherever expressed, were premised on separate measurements. This opinion was of technical experts constituted as arbitrators, who were versed in contractual interpretation of the type of work involved; they also had first hand experience as engineers who supervised such contracts. When the predominant view of these experts pointed to one direction, i.e., a composite measurement, the question is what really is the role of the court under Section 34 the Act. (Para 20)

When a majority award is challenged by the aggrieved party, the focus of the court and the aggrieved party is to point out the errors or illegalities in the majority award. The minority award (or dissenting opinion, as the learned authors point out) only embodies the views of the arbitrator disagreeing with the majority. There is no occasion for anyone- such as the party aggrieved by the majority award, or, more crucially, the party who succeeds in the majority award, to challenge the soundness, plausibility, illegality or perversity in the approach or conclusions in the dissenting opinion. That dissenting opinion would not receive the level and standard of scrutiny which the majority award (which is under challenge) is subjected to. Therefore, the so-called conversion of the dissenting opinion, into a tribunal’s findings, [in the event a majority award is set aside] and elevation of that opinion as an award, would, with respect, be inappropriate and improper. (Para 27)

In view of the findings recorded earlier, this court is of the opinion that all the appeals have to succeed. Therefore, C. A. No. 4658/2023, C. A. No. 4659/2023; C. A. No. 4660/2023; C. A. No. 4661/2023 and C. A. No. 4662/2023 are allowed; all judgments of the Delhi High Court, which were the subject matter of challenge in those appeals are set aside. The awards, which were the subject matter of challenge, and to the extent they were set aside, are hereby upheld and restored. The direction in the awards, to the extent they required compounded monthly interest payments, are modified. Instead, the NHAI shall pay uniform interest on the amounts due, on the head concerned, i.e., construction of embankment, to the extent of 12% from the date of award to the date of payment, within eight weeks from today. (Para 28)

SUPREME COURT OF INDIA

2023 STPL(Web) 214 SC

[2023INSC768]

M/S Hindustan Construction Company Limited Vs. M/S National Highways Authority Of India

Civil Appeal No(S). 4658 of 2023 With Civil Appeal No(S). 4659 of 2023 Civil Appeal No(S). 4660 of 2023 Civil Appeal No(S). 4661 of 2023 Civil Appeal No(S). 4662 of 2023-Decided on 24-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-214-SC.pdf

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Next Story

Executive instructions cannot nullify statutory rules

Assam Bonded Warehouse Rules, 1965 – Rule 7 – Refund of Charges – Administrative Order – Statutory Rules – The present writ petition contested an order issued by the Secretary to the Government of Assam, Excise Department, reintroducing establishment charges under Rule 7 of the Assam Bonded Warehouse Rules, 1965, despite their abolition by the Assam Bonded Warehouse (Amendment) Rules, 2005.

The Court held that executive instructions cannot nullify statutory rules. Citing the principle established in K. Kuppusamy case, it ruled that until a rule is amended, it remains applicable. Consequently, the impugned order was set aside as ultra vires. Regarding refund, relying on Mafatlal Industries Ltd. case, the Court directed the petitioner to present evidence to the Excise Commissioner, who would determine entitlement to refund within four months, considering whether the petitioner passed on the burden of charges to retailers. (Para 15)

GAUHATI HIGH COURT

2023 STPL(Web) 181 Gauhati

[2024 STPL 1649 Gauhati]

M/S Centenary Distilleries P Ltd. Vs. State Of Assam And 2 Ors.

WP(C) 2875 of 2014-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-181-Gauhati-2.pdf

 

Next Story

Land Disputes: Binding nature of Civil Court’s decree on Revenue Courts

Land Disputes – Binding nature of Civil Court’s decree on Revenue Courts – The instant writ petition challenged a judgment of the Assam Board of Revenue concerning a land dispute. The dispute pertained to a plot of land associated with the Dargah of Pir Saheb. The Civil Court in Title Suit No.176/1978 had decreed in favor of the Petitioners’ predecessor, declaring their right, title, and possession over the land. The State of Assam was restrained from interference. Subsequently, the Settlement Officer issued a Khatian in favor of the Petitioners’ predecessor, and a new Dag was created. However, the Assam Board of Revenue, in its impugned judgment, disregarded the Civil Court’s decree and cancelled the Khatian issued to the Petitioners’ predecessor.

This action was deemed contrary to established principles, as Civil Court decrees are binding on Revenue Courts. Therefore, the High Court set aside the impugned judgment, restoring the Khatian to the Petitioners’ predecessor. (Para 12)

GAUHATI HIGH COURT

2023 STPL(Web) 180 Gauhati

[2024 STPL 1648 Gauhati]

Sayed Moinuddin Ahmed Vs. State Of Assam And 3 Ors.

WP(C) 4701 of 2013-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-180-Gauhati.pdf

Recent Articles