Arbitration: Intense appellate review is impermissible in law – Award valid

The trial court had set aside an award made in the appellant’s favour[Dated 14.12.1997] awarding substantial amounts towards its claim, in the backdrop of a road construction contract. ( Para 1)

The contract between the parties visualized the period for completion of work to be 18 (Eighteen) English calendar months. The due date for completion of work, thus, was 22.01.1985. It was, however, not completed; several extensions were given, on the understanding that they were not due to the contractor’s fault. (Para 2)

The arbitrator, by his award[Dated 14.12.1997.], held the claimant/contractor entitled to the sum of Rs.1,50,07,000/-towards various heads and interest at 12% p.a. for the period 10.12.88 to the date of commencement of arbitration (working out to Rs.133.22 lakhs). The arbitrator rejected the state’s counter claim. (Para 4)

Both the trial court and the High Court held that the award was vitiated by the legal misconduct of the arbitrator under the old Arbitration Act[Indian Arbitration Act, 1940.]. The courts concluded that the claim was time-barred since the disputes in relation to the contract originally awarded in 1983 with the stipulation of the work being completed within eighteen months were no doubt extended with parties’ consent. It was only in 1991 that the claim for nomination of the arbitrator was made, which finally led the contractor to approach the Court under Section 8 of the Act in 1995. It was next held that the order referring the disputes to arbitration [by the Civil Judge (Senior Division)] on 25.02.1997 (in Arb. M.A. 1/1995) were in relation to the works carried on by the contractor under the contract. The courts held that the award of amounts exceeded the terms of reference in respect of at least three items. Consequently, it could not be sustained. (Para 6)

As far as the argument with regard to delay is concerned, the judgments of this court have clearly held that in such matters, the claim crystallizes upon the issuance of the final bill – which in this case was on 14.12.1992. The contractor’s complaint with respect to payment was first aired to the EE in 1988; the rejection resulted in an appeal before the SE, who never rendered his opinion or decision. Even in 1993, (after the final bill was drawn), the SE’s decision was not given. In the circumstances, the claim before the civil court for the appointment of the arbitrator: made in January, 1995 was within the period of limitation. (Para 18)

As far as the question of claims not being within the contracted period, i.e., within the 30-day time granted after foreclosure of the contract is concerned, in the opinion of the court, that issue does not arise having regard to the facts. On account of the inordinate delay (which occurred in the decision by the authorities, resulting in five extensions of time by mutual consent), the contractor voluntarily sought foreclosure. That request was acceded to by the department. There is no dispute that originally, the period of completion of the contract/works was eighteen months. The request for foreclosure, therefore, was deemed reasonable by the department and accepted upon receipt of the appellant contractor’s letter dated 06.04.1990. Such being the case, there could have been no objection to delay in submission of the claim for dispute resolution or arbitration – given that the department itself had sat over the request for settlement of disputes for more than 6 years. Moreover, the defect liability period would end only upon both parties expressing satisfaction and recording it in an agreed manner or predetermined manner. Concededly, that event never occurred. (Para 21)

In the facts of the present case, the award did not, facially disclose any error of law; damages were awarded in accordance with principles embodied in law, and the findings were based on the evidence placed before the tribunal. The ruling of the trial courts and the High Court is nothing short of intense appellate review, which is impermissible in law and beyond the courts’ jurisdiction. (Para 26)

SUPREME COURT OF INDIA

2023 STPL(Web) 196 SC

M/S S.D. Shinde Tr. Partner Vs. Govt. Of Maharashtra & Ors.

Civil Appeal Nos. 6107-6108 of 2017 With Civil Appeal No(S). 6109 of 2017-Decided on 22-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-196-SC.pdf

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Next Story

Executive instructions cannot nullify statutory rules

Assam Bonded Warehouse Rules, 1965 – Rule 7 – Refund of Charges – Administrative Order – Statutory Rules – The present writ petition contested an order issued by the Secretary to the Government of Assam, Excise Department, reintroducing establishment charges under Rule 7 of the Assam Bonded Warehouse Rules, 1965, despite their abolition by the Assam Bonded Warehouse (Amendment) Rules, 2005.

The Court held that executive instructions cannot nullify statutory rules. Citing the principle established in K. Kuppusamy case, it ruled that until a rule is amended, it remains applicable. Consequently, the impugned order was set aside as ultra vires. Regarding refund, relying on Mafatlal Industries Ltd. case, the Court directed the petitioner to present evidence to the Excise Commissioner, who would determine entitlement to refund within four months, considering whether the petitioner passed on the burden of charges to retailers. (Para 15)

GAUHATI HIGH COURT

2023 STPL(Web) 181 Gauhati

[2024 STPL 1649 Gauhati]

M/S Centenary Distilleries P Ltd. Vs. State Of Assam And 2 Ors.

WP(C) 2875 of 2014-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-181-Gauhati-2.pdf

 

Next Story

Land Disputes: Binding nature of Civil Court’s decree on Revenue Courts

Land Disputes – Binding nature of Civil Court’s decree on Revenue Courts – The instant writ petition challenged a judgment of the Assam Board of Revenue concerning a land dispute. The dispute pertained to a plot of land associated with the Dargah of Pir Saheb. The Civil Court in Title Suit No.176/1978 had decreed in favor of the Petitioners’ predecessor, declaring their right, title, and possession over the land. The State of Assam was restrained from interference. Subsequently, the Settlement Officer issued a Khatian in favor of the Petitioners’ predecessor, and a new Dag was created. However, the Assam Board of Revenue, in its impugned judgment, disregarded the Civil Court’s decree and cancelled the Khatian issued to the Petitioners’ predecessor.

This action was deemed contrary to established principles, as Civil Court decrees are binding on Revenue Courts. Therefore, the High Court set aside the impugned judgment, restoring the Khatian to the Petitioners’ predecessor. (Para 12)

GAUHATI HIGH COURT

2023 STPL(Web) 180 Gauhati

[2024 STPL 1648 Gauhati]

Sayed Moinuddin Ahmed Vs. State Of Assam And 3 Ors.

WP(C) 4701 of 2013-Decided on 7-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-180-Gauhati.pdf

Recent Articles