Consumer: Insurance – Breach of Warranty – Complaint rightly dismissed

Dismissing the consumer complaint filed by the appellant herein. (Para 1)

Charter Party Agreement dated 02.10.2006 for a sea vessel (Para 2)

The main contention of the sole respondent is that appellant’s vessel was without Class Certification on the date of the incident, being invalid and the respondent was under no contractual and/or legal obligation to reimburse the appellant. (Para 9a)

Despite knowing the stand taken by the insurance company viz. the damage which took place during the term of the first policy had not been reported to ABS, no effort was made by the complainant to produce any evidence from ABS before this Commission to prove that the aforesaid damage, including the fact that the crankshaft and connecting rods had not been replaced, was duly reported to them by the complainant. In these circumstances, it would be difficult for us to reject the report of the surveyor, who specifically stated that he had met the Principal Surveyor Mr. Ashok and Country Manager, Mr. R.C. Bhavnani of ABS to enquire whether they were informed of the damage to the port main engine of the vessel, which had occurred on 22.02.2006 and the temporary repairs carried out as per their recommendations and they were quite surprised to learn about such serious damage to the port main engine of the vessel. (Para 10)

There is no dispute that the vessel was actually classed with ABS for the period from 30.03.2006 to 03.12.2006; the issue before us is that the aforesaid Classification was obtained by concealing vital information with respect to the damage to the vessel, from the Classification Society. (Para 10)

Whether the consideration made and conclusion reached by the NCDRC as extracted above would admit of any perversity or error in its reasoning. (Para 11)

The respondent insurance company declined to honour the claim under the said policy on the basis that the non-disclosure of the fact that the engine crank shaft and connecting rods had suffered damage requiring the replacement, had not been informed by the appellant to the Classification Society for the issue of the Class Certificate and therefore, the Class Certificate would not remain valid for the reason of non-compliance of the warranty requirement. The appellant would however contend that the insurance company having issued the policy for the earlier period and having made the payment on account for the replacement, being aware of the repairs carried out and having gone on a voyage to deliver the booked cargo cannot now decline and it was for the respondent insurance company to make appropriate inquiries before issuing the policy. It is in that background a consideration was made by the NCDRC. (Para 13)

Since the insurance coverage to be provided by the insurer is based on such Class Certificate which is assumed to have been issued by the Classification Society after keeping in view all aspects including the defects if any brought to their notice. It is in that light the provisions extracted above becomes relevant as to the circumstance under which the Class will be suspended and the Certificate of Classification will become invalid in the circumstances stated therein, which also refers to such suspension and invalidation, if any damage, failure or deterioration repair has not been completed as recommended. (Para 16)

The entire issue in the instant case would hinge on the aspect as to whether the appellant had brought any material on record, either when the claim was lodged or before the NCDRC to indicate that the damage to the engine crank shaft which was required to be replaced and on account of which payment had been obtained, had been factually replaced, or if it had not been replaced, whether it was reported to ABS so that the Classification Society would have thereafter assessed as to whether even in that circumstance where the replacement had not been made, whether the repairs carried out were sufficient to certify the seaworthiness of the vessel. On being aware, an informed decision was to be taken to issue the Class Certificate. In the instant case, no such material was brought on record. (Para 17)

Keeping in view the consideration made by us hereinabove and also taking note of the provisions relating to warranty and the manner in which the Classification Certificate is issued, in the instant facts the appellant had failed to establish that the warranty class had not been breached by them and in that context the seaworthiness or otherwise at the point of accident is not of relevance. In that circumstance, we are of the opinion that the NCDRC having considered the relevant aspects of the matter in its correct perspective has arrived at its conclusion, which would not call for interference. (Para 24)

SUPREME COURT OF INDIA

2023 STPL(Web) 162 SC

[2023 INSC 697]

SUPREME COURT OF INDIA

Hind Offshore Pvt. Ltd. Vs. Iffco – Tokio General Insurance Co. Ltd.

Civil appeal no. 7228 of 2015-Decided on 9-8-2023

https://stpllaw.in/wp-content/uploads/2023/08/2023-STPLWeb-162-SC.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles