NDPS: Serious doubts about seizure – Conviction set aside

Sub-section (2) of Section 52A of the NDPS Act mandates a competent officer to prepare an inventory of such narcotic drugs with adequate particulars. This has to be followed through an appropriate application to the Magistrate concerned for the purpose of certifying the correctness of inventory, taking relevant photographs in his presence and certifying them as true or taking drawal of samples in his presence with due certification. Such an application can be filed for anyone of the aforesaid three purposes. The objective behind this provision is to have an element of supervision by the magistrate over the disposal of seized contraband. Such inventories, photographs and list of samples drawn with certification by Magistrates would constitute as a primary evidence. Therefore, when there is non-compliance of Section 52A of the NDPS Act, where a certification of a magistrate is lacking any inventory, photograph or list of samples would not constitute primary evidence. (Para 5)

The obvious reason behind this provision is to inject fair play in the process of investigation. Section 52A of the NDPS Act is a mandatory rule of evidence which requires the physical presence of a Magistrate followed by an order facilitating his approval either for certifying an inventory or for a photograph taken apart from list of samples drawn. (Para 6)

Before any proposed disposal/destruction mandate of Section 52A of the NPDS Act requires to be duly complied with starting with an application to that effect. A Court should be satisfied with such compliance while deciding the case. The onus is entirely on the prosecution in a given case to satisfy the Court when such an issue arises for consideration. Production of seized material is a factor to establish seizure followed by recovery. One has to remember that the provisions of the NDPS Act are both stringent and rigorous and therefore the burden heavily lies on the prosecution. Non-production of a physical evidence would lead to a negative inference within the meaning of Section 114(g) of the Indian Evidence Act, 1872 (hereinafter referred to as the Evidence Act). The procedure contemplated through the notification has an element of fair play such as the deposit of the seal, numbering the containers in seriatim wise and keeping them in lots preceded by compliance of the procedure for drawing samples. (Para 8)

The memorandum of informer’s information dated 20.05.2010 exhibited under P-3 indicates signature of two witnesses, P.W2 and P.W6, both of them turned hostile. Though they admitted their signature it was clearly deposed that they were not present at the scene of occurrence. In our considered view the Court below have wrongly construed the evidence, in fact these two witnesses were party to most of the exhibits running upto 13. Search warrant under Exhibit P-4 acknowledge the fact that procedure contemplated under the NDPS Act has not been followed. As noted, one of the witnesses to the seizure memo has not been examined while the other turned hostile. Both the witnesses to the arrest memo have not been examined. On the issue of non-production of narcotic substance and panch witnesses turning hostile we wish to reiterate the decision of this Court in Jitendra v. State of M.P., (2004) 10 SCC 562: (Para 11)

There is no explanation either for non-production of the seized materials or the manner in which they are disposed of. No order passed by the Magistrate allowing the application, if any, filed under Section 52A of the NDPS Act. P.W.10, Executive Magistrate has deposed to the fact that he did not pass any order for the disposal of the narcotics substance allegedly seized. Similarly, P.W.12 who is In-charge of Malkhana also did not remember any such order having been passed. (Para 12)

There is a serious doubt with respect to the seizure. P.W.5 who was a police officer himself had deposed on the existence of the very same seized materials even before the occurrence. This testimony which destroys the very basis of the prosecution case has not even been challenged. (Para 14)

Both the Courts have mechanically placed reliance on the FSL Report while taking the statement of P.W.11 as the gospel truth. The views expressed by him can at best be taken as opinion at least on certain aspects. There are too many material irregularities which create a serious doubt on the very case of the prosecution. On a proper analysis we have no hesitation in holding that the impugned judgments are liable to be set aside and the appellant is to be acquitted by rendering the benefit of doubt. (Para 14)

In the result, the appeal is allowed. The conviction and sentence rendered by the Additional Sessions Judge, Special Court NDPS, Jaora, District Ratlam, Madhya Pradesh in Special Sessions No. 19/2010 as confirmed by the High Court of Madhya Pradesh in Criminal Appeal No. 6163 of 2017 stands set aside. (Para 15)

SUPREME COURT JUDGMENT

Citation:STPL(Web) 75 SC

MANGILAL Vs. STATE OF MADHYA PRADESH

Criminal Appeal No. 1651 of 2023-Decided on 12-7-2023

Click to See Full Text of Judgment: 2023 STPL(WEB) 75 SC

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles