Prosecution Sanction required When an act, though in excess of the duty, was reasonably connected with the discharge of official duty

Where this Court made a distinction between an act, though in excess of the duty, was reasonably connected with the discharge of official duty and an act which was merely a cloak for doing the objectionable act.

No public servant is appointed with a mandate or authority to commit an offence. Therefore, if the observations contained in paragraph 50 of the decision in Parkash Singh Badal are applied, any act which constitutes an offence under any statute will go out of the purview of an act in the discharge of official duty. The requirement of a previous sanction will thus be rendered redundant by such an interpretation.

In view of the above, we uphold the contention advanced on behalf of A-1 that the prosecution ought to have taken previous sanction in terms of Section 197(1) of the Code, for prosecuting A-1, for the offences under the IPC.

Accomplice as Witness

Section 133 of the Indian Evidence Act, 1872 declares an accomplice to be a competent witness and that a conviction is not illegal merely because it proceeds upon the uncorroborated testimony of an accomplice. However, while considering the import of Section 133. this Court held in M.O. Shamsudhin vs. State of Kerala[(1995) 3 SCC 351] that the court is bound to take note of a precautionary provision contained in Illustration (b) to Section 114 of the Evidence Act, which provides that an accomplice is unworthy of credit unless he is corroborated in material particulars.

For invoking Section 73, there must first have been some signature or writing admitted or proved to the satisfaction of the Court, to have been written or made by that person. The Section empowers the Court also to direct any person present in Court to write any words or figures for the purpose of enabling the Court to compare the words or figure

There was no signature or writing available before the High Court, which had been admitted or proved to the satisfaction of the Court to have been written or made. The High Court did not also direct A-7 to write any words or figures for the purpose of enabling a comparison. Without following the procedure so prescribed in Section 73, the High Court invented a novel procedure, to uphold the conviction handed over by the Trial Court through a wrong reasoning.

In fact, the High Court considered Exhibit P-75 to be the document containing the admitted handwritings and signatures of A-7 and compared what was found therein with the handwritings/signatures found in Exhibits P-66, P-76, P-90 and P-92.

But what was contained in Exhibit P-75 was never admitted by A- 7 to be in his handwriting. Exhibit P-75 was marked through PW-30, the handwriting expert, and not even by the I.O. At least if the I.O. had identified and marked the specimen writings and signatures of A-7 as Exhibit P-75, it was possible for the prosecution to contend that the specimen signatures stood proved. But the I.O. did not identify Exhibit P-75. PW-30 through whom Exhibit P-75 was marked did not directly obtain the specimen writings of A-7. The statement of PW-30 that the specimen writings of A-7 are in Exhibit P-75 was only hearsay evidence, as he did not directly obtain those specimen signatures. Thus, Exhibit P- 75 never stood proved.

Even in the questioning under Section 313 of the Code, no specific question was put to A-7 whether Exhibits P-66, P-76, P-90, P-92 and P- 75 were in his handwritings and whether they contained his signatures. Therefore, what was contained in Exhibit P-75 was not even admitted signatures.

In the absence of either admission or proof of the admitted signatures, the High Court could not have resorted to Section 73 of the Evidence Act.

Supreme Court Judgment

SRINIVASULU Vs. STATE REP. BY THE INSPECTOR OF POLICE, 

Citation: 2023 STPL(WEB) 9 SC

Criminal Appeal No. 2417 of 2010 With Criminal Appeal No.16 of 2011 Criminal Appeal No.2444 of 2010-Decided on 15-6-2023

Click to See Full Text of Judgment: 2023 STPL(WEB) 9 SC

https://stpllaw.in/wp-content/uploads/2023/06/2023-STPLWEB-9-SC-1.pdf

Next Story

Consumer

Next Story

Contract: Demurrage not allowed

Indian Contract Act, 1872 – Demurrage – Contractual Liability – Liquidated Damages – Breach of Contract – Adjudication of Claims – The petitioner, engaged in transportation business, participated in a competitive bidding process and was awarded a transportation contract by the Food Corporation of India (FCI). Dispute arose when FCI began deducting demurrage charges from petitioner’s bills for alleged delay in unloading wagons, despite petitioner not being responsible for wagon unloading.

The petitioner contested the deduction, arguing that as per the contract, demurrage cannot be unilaterally imposed by FCI unless liability is determined through due process of law.

The Court examined the relevant contract clause, which allowed FCI to recover costs, damages, etc., due to contractor’s negligence, but found it did not specifically authorize demurrage deduction.

Relying on the Supreme Court precedent in Food Corporation of India vs. Abhijit Paul, the Court held that demurrage could not be levied on the petitioner as the contract did not assign the task of wagon unloading to them.

The absence of a liquidated damages clause in the contract further supported the Court’s decision. The Court directed FCI to refund the deducted demurrage amount and refrain from further deductions, unless liability is determined through lawful adjudication.The order did not prevent FCI from seeking damages through proper legal channels. (Para 12, 15, 18, 22)

GAUHATI HIGH COURT

2023 STPL(Web) 184 Gauhati

[2024 STPL 1652 Gauhati]

Hi Speed Logistics Pvt Ltd. Vs. Food Corporation Of India And 5 Ors.

WP(C) 6317 of 2022-Decided on 8-11-2023

Next Story

Breach of peace: It must disturb public order, not just personal peace

Code of Criminal Procedure, 1973 – Sections 145, 146- Breach of peace – Emergency situation – Possession dispute – Civil litigation – Non-application of mind – Proceeding under Section 145 – Attachment under Section 146 – The application under Section 482 of the Code of Criminal Procedure, 1973 challenges the orders by the Executive Magistrate, concerning a dispute under Section 145 of the Code of Criminal Procedure, 1973 and subsequent attachment under Section 146(1) of the same.

The petitioner contests the legality of both orders, asserting that the initiation of the proceeding and the attachment were illegal and an abuse of process. It’s argued that the jurisdiction under Section 145 can only be invoked if there’s a likelihood of a breach of peace, which wasn’t sufficiently demonstrated in this case.

The petitioner highlights that the attachment order was passed ex-parte without affording them an opportunity to respond, which is contrary to the exceptional circumstances required for such an order. Reference is made to legal precedent discouraging parallel criminal proceedings when a civil litigation is pending regarding property possession, emphasizing the binding nature of civil court decrees.

The respondents counter by claiming entitlement to the land based on a partition deed and subsequent court judgments. They argue that emergency circumstances justified the attachment due to the petitioner’s attempt to construct on disputed land.

Legal precedents are cited to emphasize that the existence of an emergency, not just the use of the term “emergency,” warrants attachment under Section 146.

The judgment critically examines the orders and the circumstances leading to them. It observes discrepancies between the assertions made in the complaint and police report, highlighting the absence of clear grounds for apprehension of breach of peace.The judgment reiterates the requirement for a dispute likely to cause a breach of peace under Section 145, emphasizing that it must disturb public order, not just personal peace.

It concludes that the impugned orders suffer from non-application of mind and jurisdictional error, resulting in injustice to the petitioner. Consequently, both orders are quashed, and the petition is allowed. Important Paragraph Numbers of Judgment: (Para 13, 19, 30, 31)

GAUHATI HIGH COURT

2023 STPL(Web) 183 Gauhati

[2024 STPL 1651 Gauhati]

Md. Osman Ali Saikia And Anr. Vs. Chand Mahamod Saikia And 2 Ors.

Crl.Pet. 239 of 2021-Decided on 8-11-2023

https://stpllaw.in/wp-content/uploads/2024/05/2023-STPLWeb-183-Gauhati.pdf

 

Next Story

Electricity: Outstanding arrears from previous owner

Constitution of India, Article 226 – Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 – Electricity Act, 2003 – Section 43, 49, 50, 56 – Electricity – Outstanding arrears from previous owner – The petitioner, a partnership firm, sought a writ petition under Article 226 challenging a decision by the Assam Power Distribution Company Limited (APDCL) to deny a new electricity connection to their premises due to outstanding arrears from previous electricity bills.

The court directed interim relief for immediate electricity connection, subject to 50% payment of outstanding dues, with the remaining 50% to be paid upon dismissal of the writ petition.

The petitioner participated in an auction sale of a property and purchased a portion of land with a Business Centre cum Market Complex. They subsequently applied for a new electricity connection, which was denied by APDCL citing outstanding dues.

The court referred to the Assam Electricity Regulatory Commission [Electricity Supply Code and Related Matters] Regulations, 2004 and the Electricity Act, 2003. It cited a Supreme Court decision (K.C. Ninan vs. Kerala State Electricity Board) regarding the liability of auction purchasers for previous dues in properties sold on ‘as is where is’ basis.

The court dismissed the writ petition, holding the petitioner liable for outstanding electricity dues as per the auction sale agreement. It directed the petitioner to pay the outstanding dues as per the interim order, with APDCL waiving the accrued interest on the principal dues. (Para 15, 16)

GAUHATI HIGH COURT

2023 STPL(Web) 182 Gauhati

[2024 STPL 1650 Gauhati]

M/S Borah And Companyjiban Phukan Nagar Vs. Assam Power Distribution Company Ltd. And 3 Ors.

WP(C) 989 of 2014-Decided on 7-11-2023

2023 STPL(Web) 182 Gauhati

Recent Articles