The High Court of Himachal Pradesh set aside the Financial Commissioner’s order directing the vesting of resort land in the State under Section 118(2) of the Himachal Pradesh Tenancy and Land Reforms Act, 1972. It held that vesting is not automatic upon the expiry of two years, cannot be ordered where delay stems from circumstances beyond the permission holder’s control such as the Managing Director’s death, and is satisfied by meaningful, phased development steps.
- Background and Impugned Order: The petitioner was granted permission on 24.01.1994 under Section 118 of the Himachal Pradesh Tenancy and Land Reforms Act, 1972 to purchase 05-10 bighas of land in Village Sakori, District Solan, for constructing a hotel/resort. After initiating vesting proceedings in 2009, the District Collector dropped them on 25.07.2014, and the Divisional Commissioner dismissed the State’s appeal on 29.08.2017, before the Financial Commissioner (Appeals) reversed those orders on 02.04.2026.
- Omission of Time Frame in Permission Letter: The permission order directed use of the land for the permitted purpose without stating a two-year period. A permission holder is primarily obligated to follow the terms stated in the permission letter and cannot be faulted merely because the issuing authority left out the statutory time frame.
- Non-Automatic Vesting and Conscious Default: Vesting under the second proviso to Section 118(2)(i) is not automatic or instant upon expiry of the period, and requires an objective inquiry and compliance with natural justice. Drawing on Ravinder Chauhan v. State of H.P., M/s Barog Resorts Pvt. Limited, and M/s Noble House Creation Pvt. Ltd., vesting is improper unless failure stems from conscious default, negligence, or refusal rather than causes beyond the holder’s control, such as the undisputed death of the project’s Managing Director.
- Meaning of Putting Land to Use: The phrase “shall put the land to such use for which the permission has been granted” does not require completing an entire resort from start to finish within two years. Because resort construction proceeds in phases, building a 350–400 meter road, erecting labour huts, and laying pillar foundations constituted cogent, meaningful steps toward the permitted purpose.
- Final Relief: The High Court quashed the Financial Commissioner’s order dated 02.04.2026 and granted the petitioner one and a half years from the date of the order to complete construction, subject to vesting in the State of Himachal Pradesh under Section 118(2) upon default.
STPL (Web) 2026 HP 797
M/s Rikhi Resorts Private Limited vs. State of Himachal Pradesh (D.O.J. 16.11.2026)