The petitioner filed a writ petition under Article 226 of the Constitution of India, seeking a mandamus to direct the Himachal Pradesh State Electricity Board to install a three-phase electricity connection for which she had applied and deposited the requisite charges. Despite a lapse of over a decade, the connection was withheld on the pretext that third-party landowners had raised objections, leaving the petitioner responsible for providing a Right of Way (RoW). Examining Sections 43 and 67 of the Electricity Act, 2003, alongside Rule 3 of the Works of Licensees Rules, 2006, the High Court held that the primary statutory duty to execute works, lay lines, and clear obstacles rests strictly on the distribution licensee rather than the individual consumer. The Court allowed the petition, directing the Board to install the three-phase connection within six weeks while clarifying that the Board is free to seek administrative or police assistance from the District Magistrate to resolve any local resistance.
- Statutory Duty to Supply: Under Section 43 of the Electricity Act, 2003, a distribution licensee is statutorily bound to supply electricity to the premises of an owner or occupier upon receiving a valid application and compliance with formalities within one month, failing which penal consequences are attracted.
- Obligation to Clear Obstacles: The primary duty to carry out works, lay power lines, and clear obstacles or objections raised by third-party landowners rests on the distribution licensee, not the consumer.
- Recourse for Right of Way (RoW) Disputes: If objections are raised regarding the Right of Way, the licensee must invoke statutory mechanisms, such as seeking written permission or assistance from the District Magistrate or Commissioner of Police, rather than denying the connection to the applicant.
STPL (Web) 2026 HP 659
Veena Thakur v. HP State Electricity Board and Others (D.O.J. 10.09.2026)