Arbitration: Why Project Owners Cannot Be Forced into Contractor-CPWD Arbitrations

This petition challenged an order passed by the sole Arbitrator, which dismissed an application filed by the Indian Institute of Technology (IIT), Mandi, seeking impleadment as a respondent in ongoing arbitral proceedings between a private construction contractor (M/s Supreme Infrastructure India Limited) and the Central Public Works Department (CPWD). IIT Mandi argued that it had a deep and substantial financial interest in the project because the construction was being executed for its campus through a Memorandum of Understanding (MoU) with CPWD. The High Court of Himachal Pradesh upheld the Arbitrator’s decision, ruling that a project owner cannot be impleaded into a separate contractor-agency arbitration merely due to a financial stake or “substantial interest,” as there was an absolute lack of privity, direct participation, or intent to be bound by the separate contract’s arbitration agreement.

  • Factual & Contractual Matrix: IIT Mandi and CPWD entered into an MoU where CPWD agreed to act as the executing agency for IIT Mandi’s campus construction as a deposit work. Subsequently, CPWD independently invited bids and executed a separate contract with the private contractor. When disputes arose under that contract, the contractor initiated arbitration solely against CPWD.
  • Power of Arbitral Tribunals to Implead Non-Signatories: While reiterating the legal position from landmark Supreme Court rulings (such as Cox & Kings and Adavya Projects), the court acknowledged that Arbitral Tribunals possess the implied power under the “doctrine of implied powers” to join a non-signatory party to prevent procedural injustice and fulfill the objectives of the Arbitration and Conciliation Act, 1996.
  • The Core Requirement of Consent and Conduct: The court emphasized that an arbitral tribunal’s power to implead a non-signatory is not absolute. It strictly hinges on establishing that the non-signatory, through its conduct, negotiations, or participation in the performance or termination of the underlying contract, has explicitly or implicitly consented to be bound by the arbitration agreement.
  • Absence of Privity and Direct Role: IIT Mandi was neither a party nor a signatory to the independent contract executed between CPWD and the contractor. IIT Mandi played no active role in the pre-qualification, negotiations, execution, or performance of that specific contract. Furthermore, the claimant contractor did not seek any relief directly against IIT Mandi.
  • Apprehension of Financial Liability is Insufficient: The court held that a mere “substantial interest” in the subject matter or a generalized apprehension of financial liability (i.e., that CPWD might ultimately pass the arbitral award’s burden onto IIT Mandi under their separate MoU) does not constitute a valid legal ground to force a non-signatory into ongoing arbitral proceedings.
  • Final Verdict: Finding no perversity or legal infirmity in the Arbitrator’s rejection of IIT Mandi’s impleadment application, the High Court dismissed the writ petition.

STPL (Web) 2026 HP 472

Indian Institute of Technology, Mandi (Kamand), H.P. v. Central Public Works Department & Another (D.O.J. 29.12.2025)

Loading Viewer...

Next Story

Custodial Torture Trial Transferred To Srinagar For Victim

The Supreme Court ordered the transfer of a CBI-investigated custodial torture criminal trial from the Principal Sessions Judge, Kupwara to the Principal District and Sessions Judge, Srinagar, holding that Article 21 fair-trial protections extend to victims and that the appellant—a police constable allegedly subjected to custodial brutality—should not face avoidable travel hardship or anxiety before accused personnel on bail. Setting aside the High Court’s March 25, 2026 refusal under Section 447 BNSS, the Court directed the Srinagar court to endeavor to conclude the trial within two years.

  • Background & CBI Investigation: The appellant, a police constable, was allegedly subjected to custodial torture in February 2023 requiring surgery at SKIMS Soura, Srinagar. Following earlier proceedings and a Supreme Court judgment dated July 21, 2025 transferring the probe to the CBI, the CBI registered an FIR on July 26, 2025 and filed a chargesheet against respondent Nos. 2 to 9 under Sections 120-B, 323, 325, 330, 331, and 343 IPC, with committal to the Sessions Judge, Kupwara on November 20, 2025.
  • High Court Refusal: The High Court of Jammu and Kashmir and Ladakh at Srinagar dismissed the appellant’s transfer petition under Section 447 BNSS on March 25, 2026.
  • Victim’s Right to Fair Trial Under Article 21: The Supreme Court held that the right to a fair trial under Article 21 protects victims as well as accused persons, noting the appellant’s physical and psychological trauma, prior struggle to secure an independent CBI investigation, travel burden between Kupwara and Srinagar, and anxiety of facing accused persons currently on bail.
  • Transfer & Trial Timeline: Setting aside the High Court’s order, the Court transferred the case (UT of J&K through SHO, P.S. CBI v. Aijaz Ahmad & Others) to the Principal District and Sessions Judge, Srinagar, urged completion of the trial within two years, and clarified that no observations touch upon the merits or guilt.

2026 INSC 1274

Khursheed Ahmad Chowhan vs. Union Territory of J and K & Ors. (D.O.J. 20.11.2026)

Loading Viewer...

Next Story

Wife Retains Maintenance Lands And Gets Higher Interim Pay

The Supreme Court held that a wife cannot be compelled to surrender possession of properties given under a maintenance arrangement at the stage of deciding an application for interim maintenance under Section 24 of the Hindu Marriage Act, 1955. Setting aside the Madras High Court’s July 12, 2024 order directing restoration of agricultural and tea-estate lands to the husband, the Court allowed the wife to retain possession and enhanced interim maintenance from Rs. 4,000 to Rs. 15,000 per month from the date of the order.

  • Background & Matrimonial Dispute: Following marital discord after their October 22, 2007 marriage and the birth of a daughter on February 21, 2009, an agreement dated December 8, 2011 placed a tea estate, agricultural parcels, and a portion of a residential house in the appellant-wife’s possession for maintenance of herself and their daughter. While the husband’s divorce petition under Section 13(1)(ia) of the Hindu Marriage Act, 1955 was pending, the wife sought interim maintenance under Section 24, resulting in a March 26, 2014 order awarding Rs. 4,000 per month and Rs. 10,000 litigation expenses.
  • High Court Revision Order: On July 12, 2024, the Madras High Court partly allowed the husband’s revision petition, ordering the wife to hand over possession of the tea estate and agricultural lands while retaining the residential house, directing payment of Rs. 1,50,000 towards past maintenance, and continuing Rs. 4,000 per month future maintenance upon surrender of the agricultural properties.
  • Retention of Properties & Enhanced Maintenance: The Supreme Court ruled that the interim nature of the 2011 arrangement or the husband’s willingness to pay maintenance upon return of possession did not justify dispossessing the wife at the interim maintenance stage without assessing actual net income, cultivation expenses, and management ability. Noting that Rs. 4,000 per month had remained unchanged for over twelve years and that the daughter—now over seventeen years old—was being raised solely by the mother, the Court raised interim maintenance to Rs. 15,000 per month prospectively while preserving the Rs. 1,50,000 past maintenance direction (subject to adjustments) to be cleared within eight weeks.
  • Clarification on Merits: The Court clarified that its directions govern only interim maintenance and leave all substantive property rights and matrimonial issues open for independent adjudication.

2026 INSC 1273

B. Prema vs. B. Rajkumar (D.O.J. 25.11.2026)

Loading Viewer...

Next Story

Act Only Policy Scope And Article 142 Pay-And-Recover Power

The Supreme Court held that compulsory third-party insurance under Section 147 of the Motor Vehicles Act, 1988 does not automatically cover gratuitous occupants of a private vehicle or pillion riders on a two-wheeler under an “Act Only” policy where no additional premium was paid. However, affirming the insurer’s non-liability, the Court exercised its extraordinary power under Article 142 of the Constitution to direct the insurer to first satisfy the outstanding compensation award and recover it from the vehicle owner, setting out four cumulative requirements for such relief.

  • Accident, Claim & High Court Ruling: Following a fatal accident on April 15, 2012 involving a Tata Sumo jeep driven by its owner (Abdul Gazi) in which occupant Suryakant Pandurang Nikam died, the Motor Accident Claims Tribunal awarded Rs. 7,79,800 with 7.5% interest and ordered “pay and recover” against United India Insurance Company Ltd., finding policy breach/no passenger coverage. The Bombay High Court (Aurangabad Bench) exonerated the insurer on August 5, 2019, holding that an Act Only Policy did not cover a private-car occupant and that Tribunals/High Courts lack Article 142 powers.
  • Compulsory Coverage Under Section 147: Interpreting Sections 145(g), 146, 147, and 149 of the MV Act alongside precedents such as Asha Rani, Baljit Kaur, Tilak Singh, Sudhakaran K.V., and Balakrishnan, the Court ruled that being a person other than the insured or insurer does not automatically bring an occupant or pillion rider within compulsory Act Only coverage. Coverage depends on the statutory scheme and the specific risks undertaken in the policy.
  • Article 142 Framework for Pay and Recover: Examining Supreme Court Bar Association, Shilpa Sailesh, and earlier pay-and-recover decisions, the Court held that absence of statutory/contractual liability is not an absolute bar to Supreme Court intervention under Article 142 (a power belonging to the Supreme Court alone, not Tribunals or High Courts). Exceptional pay-and-recover relief requires satisfying four cumulative criteria: (i) established, judicially determined liability; (ii) exceptional necessity to prevent substantial injustice; (iii) necessity and proportionality; and (iv) procedural fairness with effective recovery safeguards.
  • Application & Operative Directions: Considering the judicially determined liability against the owner, over fourteen years elapsed since the 2012 accident, and the elderly widow appellant’s financial and medical hardship, the Court directed the insurer to deposit the verified unpaid compensation and interest within eight weeks of the Tribunal’s four-week determination, and recover it from the owner through execution proceedings before the Tribunal without filing a separate suit.

2026 INSC 1272

Sukumarbai & Ors. vs. United India Insurance Company Ltd. & Anr. (D.O.J. 25.11.2026)

Loading Viewer...

Next Story

Eligibility Alone Cannot Confer Absorption Without A Sanctioned Post

The Supreme Court held that acquiring academic eligibility on a given date does not entitle a lecturer appointed on an unsanctioned post to retrospective absorption from that eligibility date when no sanctioned or pre-cut-off recommended post was available. Affirming the Division Bench of the Jharkhand High Court, the Court upheld the appellant’s absorption with effect from June 1, 2003—when a sanctioned post fell vacant upon retirement—as approved by the Justice S.B. Sinha Commission.

  • Background & Appointments: The appellant was appointed on February 22, 1986 as a Lecturer in Hindi on a fifth post at S.J.S.N. College, Garhwa, without possessing the requisite minimum qualification on that date, which he acquired on December 5, 1987. Four senior lecturers were already working against the four sanctioned posts in Hindi, while the University’s forwarding of the college’s proposal for additional posts (5th to 8th) occurred on July 11, 1987, after the March 31, 1987 cut-off date.
  • Commission Reports & Absorption Order: Following the Justice S.C. Agrawal Commission report (accepted by the Supreme Court in State of Bihar v. Bihar Rajya MSESKK Mahasangh) and subsequent individual scrutiny by the Justice S.B. Sinha Commission, the appellant’s absorption was upheld with effect from June 1, 2003 following the retirement of lecturer Ram Naresh Pathak on May 31, 2003.
  • Single Judge vs. Division Bench: A Single Judge of the Jharkhand High Court allowed the appellant’s writ petition and directed consideration of absorption from December 5, 1987 based on his listing in Annexure IV-A of the Agrawal Commission report. On Letters Patent Appeal, the Division Bench set aside the Single Judge’s order, holding that eligibility without a sanctioned post before the cut-off date conferred no right to earlier absorption.
  • Supreme Court Ruling: The Supreme Court ruled that Annexure IV-A only lists teachers eligible to be considered for absorption according to eligibility dates and cannot create a right where no sanctioned or timely recommended post existed. Noting also that the Justice Sinha Commission found the relied-upon letter not genuine and properly recognized absorption against a subsequent superannuation vacancy, the Court dismissed the appeal.

2026 INSC 1271

Brij Kumar Mishra vs. Nilamber Pitambar University & Ors. (D.O.J. 25.11.2026)

Loading Viewer...

Recent Articles